FIR08-00255
| INSP-Final Inspection | 3/27/2009 | 3/27/2009 | | P | |
|
|
Contact Rafe Phone#: ###-####
|
FIR09-00137
| INSP-Final Inspection | 4/1/2009 | 4/2/2009 | 4/2/2009 4:16:44 PM | P | PASS |
|
|
Items on issued correction notice verified for completion, fire sprinkler permit finaled.
|
FIR08-00737
| INSP-Sprinkler Rough-in/Hydro | 4/2/2009 | 4/2/2009 | 4/2/2009 4:14:52 PM | P | PART |
|
|
New dry system piping hydrostatic test completed, discussed schedule for 24 hr. air testing next week.
|
FIR07-01051
| INSP-Sprinkler Rough-in | 4/1/2009 | 4/2/2009 | 4/2/2009 4:11:56 PM | P | PART |
|
|
See approved plans for overhead okayed for cover at drop ceilings 1st and 2nd floors various locations, also approved dry pendent install at the kitchen coolers.
|
BLD09-00080
| FIRE-Final Inspection | 4/2/2009 | 4/2/2009 | 4/2/2009 2:07:03 PM | P | PASS |
|
|
Noted correction items finished, fire life safety finaled.
|
FIR08-00835
| FIR-Aging Inspection | 4/2/2009 | 4/2/2009 | 4/2/2009 2:06:07 PM | | DONE |
|
|
Work in progress construction underway.
|
FIR09-00135
| INSP-Final Inspection | 4/2/2009 | 4/2/2009 | 4/2/2009 2:04:55 PM | A | PASS |
|
|
Final fire sprinkler inspection passed, permit finaled.
|
FIR09-00163
| INSP-Final Inspection | 4/1/2009 | 4/2/2009 | 4/2/2009 2:03:58 PM | A | PASS |
|
|
Fire alarm testing completed acceptable after corrections made while on site, verified as-builts for field modifications, permit finaled.
|
FIR08-00766
| INSP-Sprinkler Rough-in/Hydro | 4/2/2009 | 4/2/2009 | 4/2/2009 1:45:42 PM | A | PART |
|
|
See dated plan notes for UG installation work okayed.
|
BLD09-00301
| FIRE-Final Inspection | 4/2/2009 | 4/2/2009 | 4/2/2009 1:44:08 PM | A | PART |
|
|
See plan annotations for work completed to date.
|