Inspections for the day of: Tuesday, April 2, 2013.
Number of inspections: 16
Percentage of inspections complete: 94 %
Percentage of inspections not complete: 6 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MIS13-00072 FIR-Conference3/27/20133/27/2013 P 
waiting on Stephanie to check documents
FIR12-00737 FIR-Aging Inspection4/2/20134/2/20134/10/2013 3:25:00 PM NR
wip
FIR12-00001 FIR-Aging Inspection4/2/20134/2/20134/10/2013 7:30:33 AM NR
Rick was going to follow up on job status.
FIR12-00685 FIR-Aging Inspection4/2/20134/2/20134/3/2013 7:19:55 AM NR
Work is in progress
BLD12-03082 FIRE-Final Inspection4/2/20134/2/20134/2/2013 3:53:55 PMPPASS
Life safety passed
BLD13-00725 FIRE-Final Inspection4/2/20134/2/20134/2/2013 2:59:38 PMPFAIL
Two pendant heads are overspaced off of the north wall in the Retail area. A temporary occupancy will be ok when the sprinkler contractor has submitted for approval.
BLD11-01875 FIRE-Final Inspection4/2/20134/2/20134/2/2013 2:49:03 PMPFAIL
Provide accessible hardware on the new doors as per the approved plans. Repair the exit signs as discussed.
FIR12-00574 INSP-Sprinkler Rough-in/Hydro4/1/20134/2/20134/2/2013 2:35:13 PMPPASS
The oh hydro of the 4" riser/steim passed. The 24 hour air test of the dry system was startedat 12:00 with 44psi on the guage. Previous correction items in the shop areas have been corrected.
BLD12-01975 FIRE-Final Inspection4/1/20134/2/20134/2/2013 1:52:07 PMPPASS
life safety passed
BLD13-00652 FIRE-Final Inspection4/2/20134/2/20134/2/2013 1:44:31 PMPFAIL
Repair the two emergency lights. All other items appear ok.
FIR13-00109 INSP-Supply line flush4/2/20134/2/20134/2/2013 1:06:21 PMPPASS
This is an ug flush.
FIR12-00717 INSP-Sprinkler Rough-in4/1/20134/2/20134/2/2013 12:57:52 PMAPASS
See the city approved plans for location where the sprinkler piping can be covered
FIR13-00108 INSP-Supply line flush4/2/20134/2/20134/2/2013 12:54:51 PMPPASS
Thi is an ug flush.
FIR13-00107 INSP-Supply line flush4/2/20134/2/20134/2/2013 12:53:25 PMPPASS
This is an ug flush.
FIR13-00094 INSP-Final Inspection4/1/20134/2/20134/2/2013 10:04:31 AMAFAIL
I noted that the candella had been changed on several devices and an additional devices need to be provided in the conference room and the break room. No testing was done. As-builts will be needed showing the additional/changes of the devices.
FIR13-00047 INSP-Final Inspection4/1/20134/2/20134/2/2013 10:02:32 AMAPASS
Permit finaled