MEC14-01212
| Final | 4/1/2014 | 4/2/2014 | 4/2/2014 4:23:54 PM | P | PASS |
|
|
WE FIXED THE: Upper combustion air duct is almost completely covered by insulation & the roof joist running through it. the duct needs to be extended above the insulation level to prevent blocking. Phone #: ###-#### >> Inspection requested via web by Manuel Acuna
|
MEC12-01787
| Mec-Aging Inspection | 4/2/2014 | 4/2/2014 | 4/2/2014 3:53:29 PM | | CANC |
|
|
No calls
|
MEC14-01250
| Final | 4/2/2014 | 4/2/2014 | 4/2/2014 2:45:22 PM | P | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by April Thomas
|
MEC14-01213
| Rough-in | 4/1/2014 | 4/2/2014 | 4/2/2014 2:17:32 PM | P | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Dan Otero
|
ESC14-00033
| Random Inspection | 4/2/2014 | 4/2/2014 | 4/2/2014 2:11:14 PM | P | DONE |
|
|
Called Kent, left him a message saying needs to clean up the mud on the sreet in front of the property.
|
MEC14-00893
| Rough-in | 4/2/2014 | 4/2/2014 | 4/2/2014 1:32:28 PM | P | FAIL |
|
|
Please make it as late as possible. Thank you. Phone #: ###-#### >> Inspection requested via web by Dan Otero Fireplace is not fastened to the structrure. It's pulled out from the framing.
|
MEC14-01028
| Final | 4/1/2014 | 4/2/2014 | 4/2/2014 11:53:52 AM | A | CANC |
|
|
Duct Blast at 11:30 am. Call Joel at ###-#### if you need to reschedule Phone #: ###-#### >> Inspection requested via web by Debbie Marino
|
MEC14-01028
| Pressure Test | 4/2/2014 | 4/2/2014 | 4/2/2014 11:53:27 AM | A | PASS |
|
|
20LB gas pressure test pass
|
MEC14-01028
| Rough-in | 4/1/2014 | 4/2/2014 | 4/2/2014 11:46:27 AM | A | PASS |
|
|
Duct Blast at 11:30 am. Call Joel at ###-#### if you need to reschedule Phone #: ###-#### >> Inspection requested via web by Debbie Marino
|
MEC14-01190
| Rough-in | 4/1/2014 | 4/2/2014 | 4/2/2014 11:16:03 AM | A | PASS |
|
|
Duct blaster test at 11:00 am. Please call with any questions or concerns. Thank you. Phone #: ###-#### >> Inspection requested via web by Jennifer Roy
|
MEC14-01030
| Rough-in | 3/31/2014 | 4/2/2014 | 4/2/2014 10:59:33 AM | A | PASS |
|
|
Duct Blast at 10 am. Call Joel at ###-#### to reschedule if needed. Phone #: ###-#### >> Inspection requested via web by Debbie Marino
|
MEC14-01030
| Pressure Test | 3/31/2014 | 4/2/2014 | 4/2/2014 10:59:00 AM | A | PASS |
|
|
Duct Blast at 10 am. Call Joel at ###-#### to reschedule if needed. Phone #: ###-#### >> Inspection requested via web by Debbie Marino - 20LB gas pressure test pass.
|
MEC14-00406
| Final | 4/1/2014 | 4/2/2014 | 4/2/2014 9:30:40 AM | A | FAIL |
|
|
Phone #: ###-#### >> Inspection requested via web by Randy Hart - No air balance report on site.
|
MEC14-00699
| Final | 4/1/2014 | 4/2/2014 | 4/2/2014 9:29:21 AM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Dan Otero
|
MEC14-01178
| Rough-in | 4/1/2014 | 4/2/2014 | 4/2/2014 9:05:11 AM | A | PASS |
|
|
john Phone #: ###-#### Ok to cover.
|
MEC14-00072
| Final | 3/31/2014 | 4/2/2014 | 4/1/2014 4:03:00 PM | A | CANC |
|
|
Please contact Jason with any questions. Phone #: ###-#### >> Inspection requested via web by Lisa Whitney Inspection cancelled from web by: Lisa Whitney
|