FIR08-00234
| INSP-Alarm Testing | 4/20/2009 | 4/20/2009 | 4/20/2009 4:11:52 PM | P | DONE |
|
|
The items inspected today were the firemans phones. The phone operated except the 15th floor east which would cut out and needs replaced. Also phone jacks are shown to be installed on the exterior stairways but have not been installed.
|
FIR09-00019
| INSP-Final Inspection | 4/20/2009 | 4/20/2009 | 4/20/2009 3:24:01 PM | P | CANC |
|
|
Could not perform the inspection due to time constraints. Billy will reschedule for tomorrow.
|
FIR08-00855
| INSP-Sprinkler Rough-in | 4/17/2009 | 4/20/2009 | 4/20/2009 3:21:17 PM | P | PART |
|
|
Seven upright heads need to be added as marked on the city approved plans. One piece of sprinkler piping on the plans has no designation and 4" piping has been installed where 3" is shown on the plans. Sprinkler piping can be covered except where these problems are located.
|
FIR09-00120
| INSP-Final Inspection | 4/17/2009 | 4/20/2009 | 4/20/2009 3:18:53 PM | A | PART |
|
|
A temporary occupancy was given with sam rogers permission. The items that were tested and passed today were the phone lines from the existing silent knight panel to the central station, a trouble signale from the new panel to the silent knight panel, tamper switch, PIV switch, flow switch and hvac shutdown from the activation of one smoke detector. No other items were inspected. The other items will be inspected when the monitoring agreement is complete and the existing silent knight panel is removed and the phone lines attached to the new simplex panel.
|
FIR07-00524
| INSP-Final Inspection | 4/17/2009 | 4/20/2009 | 4/20/2009 9:14:48 AM | P | CANC |
|
|
I spoke to TIm about rescheduling this inspection due to a conflict of interest.
|
BLD09-00495
| FIRE-Final Inspection | 4/16/2009 | 4/20/2009 | 4/20/2009 9:13:34 AM | A | PASS |
|
|
life safety passed
|