BLD05-00850
| FIRE-Final Inspection | 4/20/2006 | 4/21/2006 | 4/21/2006 4:27:12 PM | P | PASS |
|
|
Life safety is acceptable.
|
BLD05-03461
| FIRE-Final Inspection | 4/21/2006 | 4/21/2006 | 4/21/2006 3:02:39 PM | P | PASS |
|
|
The building fire alarm and sprinkler permits have been finaled, life safety for the permitted seismic upgrade work is acceptable.
|
BLD04-01323
| FIRE-Final Inspection | 4/21/2006 | 4/21/2006 | 4/21/2006 2:59:11 PM | P | PASS |
|
|
Fire life safety is acceptable, c/n items are complete.
|
FIR06-00057
| INSP-Final Inspection | 4/20/2006 | 4/21/2006 | 4/21/2006 2:58:20 PM | A | PASS |
|
|
Fire alarm work passed field inspection.
|
FIR06-00053
| INSP-Sprinkler Rough-in/Hydro | 4/20/2006 | 4/21/2006 | 4/21/2006 12:21:15 PM | P | PART |
|
|
Hydrostatic test for the UG supply and the overhead system both passed inspection. Rough-in inspection is satisfactory as well, need to provide a ball drip at the FDC, and signage at the FDC per review notes.
|
FIR06-00236
| INSP-Final Inspection | 4/19/2006 | 4/21/2006 | 4/21/2006 10:12:56 AM | A | PASS |
|
|
FACP tested satisfactory, full functionality verified, inspection passed.
|
FIR05-00297
| INSP-Final Inspection | 4/20/2006 | 4/21/2006 | 4/21/2006 10:09:37 AM | A | PASS |
|
|
Required corrections have been completed, fire sprinkler finaled.
|
FIR05-00244
| INSP-Final Inspection | 4/20/2006 | 4/21/2006 | 4/21/2006 10:08:32 AM | A | PASS |
|
|
The permitted fire sprinkler demo work has been completed, permit finaled.
|
FIR05-00239
| INSP-Final Inspection | 4/20/2006 | 4/21/2006 | 4/21/2006 10:06:42 AM | A | PASS |
|
|
UG fire supply line permit finaled.
|
FIR05-00075
| INSP-Final Inspection | 4/20/2006 | 4/21/2006 | 4/21/2006 10:04:33 AM | A | PASS |
|
|
Final fire alarm inspection passed, permit finaled.
|