BLD15-02530
| FIRE-Final Inspection | 4/21/2016 | 4/21/2016 | 4/21/2016 3:04:57 PM | P | FAIL |
|
|
No small documents on site so Bob and I did a quick walk through. I noted missing sticker and indicator at the office exit. Opticons at the two gates will need to be tested by the fire dept prior to a sign off.
|
FIR16-00230
| INSP-Final Inspection | 4/21/2016 | 4/21/2016 | 4/21/2016 3:02:37 PM | P | PASS |
|
|
Permit finaled
|
BLD16-00804
| FIRE-Final Inspection | 4/20/2016 | 4/21/2016 | 4/21/2016 12:34:52 PM | A | PASS |
|
|
Life safety passed. Single action hardware on the southwest door to be installed prior to a building inspection.
|
FIR16-00183
| INSP-Supply line flush | 4/20/2016 | 4/21/2016 | 4/21/2016 10:15:47 AM | A | PASS |
|
|
Underground supply line flush passed
|
FIR15-00907
| INSP-Conference | 4/20/2016 | 4/21/2016 | 4/21/2016 10:14:49 AM | A | DONE |
|
|
Air test started at 9:30. See pressure marked on guage.
|