FIR16-00028
| INSP-Sprinkler Rough-in/Hydro | 4/18/2016 | 4/21/2016 | 4/22/2016 9:37:11 AM | P | PART |
|
|
200 psi hydrostatic test complete for overhead fire sprinkler piping for all levels. Rough to cover inspection complete for overhead fire sprinkler piping on 1st and 2nd level, 1st and 2nd level approved for cover with exception to piping that is ran through breeze-way, this piping cannot be covered until proper freeze protection is installed and inspected. Partial cover approved for 3rd level fire sprinkler piping, fire sprinkler piping that is not in attic spaces approved for cover with exception to breeze-way piping. Fire sprinkler piping in attic spaces on 3rd level and 4th level cannot be covered until tenting inspection is completed and approved. Fire sprinkler piping crosses the entry corridor on each level, these area's cannot be covered until proper heating/ventilation is provided to keep fire sprinkler piping from freezing through the breeze-way (As addressed and stated on city approved drawings)
|
BLD14-03175
| FIRE-Final Inspection | 4/21/2016 | 4/21/2016 | 4/21/2016 4:33:03 PM | P | PASS |
|
|
Final fire sprinkler inspections complete, final fire pump relocation inspections complete, final fire alarm inspections complete. Fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
|
FIR15-00185
| INSP-Final Inspection | 4/21/2016 | 4/21/2016 | 4/21/2016 4:29:55 PM | P | PASS |
|
|
Final fire alarm inspection passed/complete
|
FIR16-00218
| INSP-Sprinkler Rough-in/Hydro | 4/18/2016 | 4/21/2016 | 4/21/2016 3:03:15 PM | P | PASS |
|
|
Rough in inspection for building standpipe complete. 200 psi hydrostatic test for building standpipe complete.
|
BLD15-02346
| FIRE-Final Inspection | 4/20/2016 | 4/21/2016 | 4/21/2016 11:22:07 AM | P | PASS |
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
|
FIR15-00794
| INSP-Final Inspection | 4/21/2016 | 4/21/2016 | 4/21/2016 11:20:04 AM | P | PASS |
|
|
Final fire alarm inspection passed/complete
|
FIR16-00116
| INSP-Supply line flush | 4/21/2016 | 4/21/2016 | 4/21/2016 11:00:45 AM | P | DONE |
|
|
Underground main line flush complete
|
FIR15-00121
| INSP-Supply line flush | 4/20/2016 | 4/21/2016 | 4/21/2016 10:59:47 AM | A | CANC |
|
|
Inspection request cancelled, incorrect FIR permit request
|
FIR15-00329
| INSP-Sprinkler Rough-in | 4/21/2016 | 4/21/2016 | 4/21/2016 9:16:46 AM | A | PART |
|
|
South supply main post indicator valve relocated to line up with tree location, underground inspection for relocation passed/complete. Relocation for north post indicator will be completed at later date.
|