BLD19-00534
| BLD-Framing/Rough-in | 4/20/2020 | 4/21/2020 | 4/21/2020 3:55:19 PM | P | PART |
|
|
Inspection on 3rd floor for approval to insulate and cover inspection on 4th floor Phone #: ###-#### Inspection requested via web by Travis Blackburn//4th floor ok to cover when fire collars are on drain pipe//3rd floor ok to insulate, fix sprinkler tenting, add fire collar to drain pipe, fix hole in joist in furnace room on two of the 4 units//
|
BLD20-01041
| BLD-Foundation | 4/21/2020 | 4/21/2020 | 4/21/2020 3:40:19 PM | P | PART |
|
|
Virtual Inspection Requested // Pat Phone #: ###-####//bar drilled to exisiting//wip//
|
BLD20-00670
| BLD-Footing | 4/21/2020 | 4/21/2020 | 4/21/2020 2:14:51 PM | P | PART |
|
|
picture of footing for point load was provided where it was needed, per the correction notice from wall inspection///appears to be rebar installed in the photo//
|
BLD19-03992
| BLD-Framing/Rough-in | 4/21/2020 | 4/21/2020 | 4/21/2020 1:34:56 PM | P | PART |
|
|
Willie - Soffit Inspection for Fire Protection Phone #: ###-####//ok to cover soffits//
|
BLD19-00532
| BLD-Wall Bracing | 4/20/2020 | 4/21/2020 | 4/21/2020 12:38:44 PM | A | PART |
|
|
Inspection for missed straps at south balconies for exterior cover. Phone #: ###-#### Inspection requested via web by Travis Blackburn//exterior straps nailed and exterior nailing ok//still need to check other hardware//
|
BLD19-00532
| BLD-Framing/Rough-in | 4/20/2020 | 4/21/2020 | 4/21/2020 12:38:03 PM | A | PART |
|
|
Partial framing inspection for 2hr lid in west corridor Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok to install shaft liner//
|
BLD20-01184
| BLD-Final | 4/17/2020 | 4/21/2020 | 4/21/2020 12:37:31 PM | A | DONE |
|
|
Inspection requested via web by Hans Weikl
|
BLD20-01184
| DOC - Permit Finaled | 4/21/2020 | 4/21/2020 | 4/21/2020 12:37:21 PM | P | PASS |
|
|
roof appears to be installed within code requirements//no access to back//
|
BLD19-04742
| BLD-Footing | 4/15/2020 | 4/21/2020 | 4/21/2020 11:28:22 AM | A | NR |
|
|
Phone #: ###-#### Inspection requested via web by Ron Ramza//need approved plans and engineering onsite//
|
BLD20-00670
| BLD-Wall Bracing | 4/20/2020 | 4/21/2020 | 4/21/2020 11:02:10 AM | A | FAIL |
|
|
Need a shear wall inspection Phone #: ###-#### Inspection requested via web by David Thompson//CN posted, need to nails or staple with correct size staples front and rear shear walls//remove wrap in areas to verify staples//add hot dip galvanized nails at pt plate//add anchor bolts at plate ends//
|
BLD20-01163
| BLD-Other | 4/20/2020 | 4/21/2020 | 4/21/2020 9:50:31 AM | A | DONE |
|
|
Inspection on a completed asphalt re-roof project. Phone #: ###-#### Inspection requested via web by Michael La Pointe
|
BLD20-01163
| DOC - Permit Finaled | 4/21/2020 | 4/21/2020 | 4/21/2020 9:50:21 AM | P | PASS |
|
|
Roof appears to be installed within code requirements//no access to back//
|
BLD19-04725
| BLD-Wall Bracing | 4/20/2020 | 4/21/2020 | 4/21/2020 9:09:31 AM | A | PASS |
|
|
Brian Phone #: ###-####//shear corrections made, engineers letter provided for corrections//
|
MIS20-00121
| BLD-Conference | 4/20/2020 | 4/21/2020 | 4/21/2020 8:55:48 AM | A | DONE |
|
|
corrction notice posted to obtain permit for re-roof//
|