PLM96-02327
| INSP - Final | 4/21/1998 | 4/22/1998 | 4/23/1998 12:00:00 AM | P | PASS |
|
|
04/22/98 323 - ###-####/EARL - AFTER 1P. - FINAL OK
|
PLM97-04073
| INSP - Final | 4/22/1998 | 4/22/1998 | 4/23/1998 12:00:00 AM | P | FAIL |
|
|
04/22/98 323 - final ###-#### - CORRECTION NEEDED - NEED UNIONS ON W.H.
|
PLM98-00091
| INSP - Final | 4/22/1998 | 4/22/1998 | 4/23/1998 12:00:00 AM | P | NH |
|
|
04/22/98 323 - final ###-#### - NO ACCESS
|
PLM98-01168
| INSP - Plumbing Rough-in | 4/22/1998 | 4/22/1998 | 4/23/1998 12:00:00 AM | P | PASS |
|
|
04/22/98 323 - jeanette ###-#### - GROUND WORK OK
|
PLM98-01176
| INSP - Final | 4/22/1998 | 4/22/1998 | 4/23/1998 12:00:00 AM | P | PASS |
|
|
04/22/98 323 - chuck ###-#### sprinkler - SPRINKLER FINAL
|
PLM98-01178
| INSP - Final | 4/22/1998 | 4/22/1998 | 4/23/1998 12:00:00 AM | P | PASS |
|
|
04/22/98 323 - brian ###-#### sprinkler - SPRINKLER FINAL
|
PLM98-01183
| INSP - Plumbing Rough-in | 4/22/1998 | 4/22/1998 | 4/23/1998 12:00:00 AM | P | PASS |
|
|
04/22/98 323 - ###-####/KEN - ROUGH-IN OK
|
PLM98-01171
| INSP - Sewer/Water lines-FINAL | 4/22/1998 | 4/22/1998 | 4/22/1998 12:00:00 AM | | PASS |
|
|
/ / 323 - SEWER AND WATER FINAL
|
PLM98-01087
| INSP - Plumbing Rough-in | 4/21/1998 | 4/22/1998 | 4/22/1998 12:00:00 AM | A | PART |
|
|
04/22/98 323 - ###-####/JOHN - AS EARLY POS. - NOT COMPLETE
|
PLM98-01110
| INSP - Final | 4/21/1998 | 4/22/1998 | 4/22/1998 12:00:00 AM | A | PASS |
|
|
04/22/98 323 - reinspection sprinkler tracy ###-#### - SPRINKLER FINAL
|
PLM98-01111
| INSP - Final | 4/21/1998 | 4/22/1998 | 4/22/1998 12:00:00 AM | A | PASS |
|
|
04/22/98 323 - reinspection sprinkler tracy ###-#### - SPRINKLER FINAL
|
PLM98-01152
| INSP - Final | 4/21/1998 | 4/22/1998 | 4/22/1998 12:00:00 AM | A | PASS |
|
|
04/22/98 323 - ###-#### water line - WATER LINE FINAL
|
PLM98-01168
| INSP - Plumbing Rough-in | 4/21/1998 | 4/22/1998 | 4/22/1998 12:00:00 AM | A | NR |
|
|
04/22/98 323 - ###-####/JENNET R/I LATE MORNING. - NOT COMPLETE
|