FIR13-00175
| INSP-Sprinkler Rough-in | 4/22/2013 | 4/22/2013 | 4/22/2013 4:51:07 PM | P | FAIL |
|
|
The plans are locked up in the job shack. No inspection was performed.
|
BLD13-00620
| FIRE-Final Inspection | 4/22/2013 | 4/22/2013 | 4/22/2013 4:39:14 PM | P | CANC |
|
|
I left message on brads Phone #: ###-#### that I was over booked and would re-schedule his inspection for tomorrow morning.
|
FIR13-00032
| INSP-Sprinkler Rough-in | 4/22/2013 | 4/22/2013 | 4/22/2013 4:32:07 PM | P | CANC |
|
|
Overbooked. Javier is going to reschedule for tomorrow.
|
BLD13-00725
| FIRE-Final Inspection | 4/22/2013 | 4/22/2013 | 4/22/2013 4:23:11 PM | P | FAIL |
|
|
Will be ok to final life safety when the project related fire sprinkler permit is complete.
|
FIR13-00160
| INSP-Final Inspection | 4/22/2013 | 4/22/2013 | 4/22/2013 4:22:10 PM | P | FAIL |
|
|
Piping as installed appears ok but there are no city approved plans on site for the inspection. Will need to be rescheduled.
|
FIR12-00108
| INSP-Sprinkler Rough-in | 4/22/2013 | 4/22/2013 | 4/22/2013 4:06:47 PM | P | CANC |
|
|
Overbooked. Rescheduled for Tim in the morning.
|
FIR13-00129
| INSP-Final Inspection | 4/22/2013 | 4/22/2013 | 4/22/2013 3:59:39 PM | P | PASS |
|
|
Permit finaled. Hood suppression system functioned correctly.
|
FIR13-00086
| INSP-Final Inspection | 4/19/2013 | 4/22/2013 | 4/22/2013 3:29:56 PM | P | PART |
|
|
See the city approved plans for location, clouded in red, where the fire alarm system has been inspected and passed. Per Jeremy with Alta Construction this is the first phase they are requesting occupancy.
|
FIR13-00086
| INSP-Conference | 4/22/2013 | 4/22/2013 | 4/22/2013 10:09:09 AM | A | DONE |
|
|
Myself, the alarm contractor and the electrician discussed the overspace ceiling mounted a/v' in the main corridor and womens restroom. Also the manual pull station in the mechanical room is mounted too high. Ceiling tile will need to be installed at the facp for the containment of smoke.
|