Inspections for the day of: Monday, April 22, 2013.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD13-00231 BLD-Framing/Rough-in4/22/20134/22/20134/22/2013 4:14:19 PMPPASS
late pm//Jim Phone #: 559-. All framing issues resolved.
BLD13-00231 BLD-Energy code compliance4/22/20134/22/20134/22/2013 4:13:53 PMPPASS
late pm//Jim Phone #: ###-####
BLD12-03273 BLD-Footing4/22/20134/22/20134/22/2013 3:02:39 PMPPART
joe Phone #: ###-####. Column pad footings for new porte cochere Per RFI from stapley engineering. Will have have special inspection.
BLD13-00387 BLD-Wall Bracing4/22/20134/22/20134/22/2013 2:00:32 PMPFAIL
Phone #: ###-#### >> Inspection requested via web by Daniel Appel. Provide approved plans for inspection.
BLD13-00931 BLD-Footing4/19/20134/22/20134/22/2013 1:37:17 PMPPASS
Marcus will be doing the installation. His cell number is ###-####. Earlier in the afternoon would probably be better. Phone #: ###-#### >> Inspection requested via web by rich prasch
BLD13-00631 BLD-Footing4/18/20134/22/20134/22/2013 1:17:00 PMPNR
ryan Phone #: ###-####. site not yet excavated for footings.
BLD13-00462 BLD-Foundation4/19/20134/22/20134/22/2013 10:24:32 AMAPART
Chris Phone #: ###-####
BLD13-00858 BLD-Footing4/19/20134/22/20134/22/2013 9:24:02 AMAPASS
Kelly Phone #: ###-####