BLD13-03221
| FIRE-Conference | 4/22/2014 | 4/22/2014 | 4/22/2014 4:42:30 PM | P | DONE |
|
|
Final pending project related fire alarm permit inspection and final- Related fire sprinkler permit finaled 4/21.
|
FIR14-00075
| INSP-Final Inspection | 4/21/2014 | 4/22/2014 | 4/22/2014 2:38:08 PM | P | PASS |
|
|
Completed remainder of acceptance test including heat detectors, verified documents box, map at the panel updated, recieved record of completion forms. Fire alarm permit finaled.
|
FIR13-00308
| INSP-Sprinkler Rough-in | 4/22/2014 | 4/22/2014 | 4/22/2014 2:32:53 PM | A | PART |
|
|
Walkthrough of the 1st and 2nd floor new office addition completed. Noted obstructions to coverage at the 2nd floor executive locker room, covered sprinkler and missing escutcheon at mechanical room. Remainder okayed.
|
BLD13-03142
| FIRE-Final Inspection | 4/22/2014 | 4/22/2014 | 4/22/2014 11:38:08 AM | A | NR |
|
|
Pending remainder of C/N items.
|
FIR13-00440
| INSP-Sprinkler Rough-in | 4/22/2014 | 4/22/2014 | 4/22/2014 11:36:29 AM | A | PART |
|
|
OH rough-in as marked on stamped plans at the lobby and reception areas okayed.
|
FIR13-00547
| INSP-Final Inspection | 4/22/2014 | 4/22/2014 | 4/22/2014 11:35:27 AM | A | PASS |
|
|
Scope of fire sprinkler work completed and passed final walkthrough.
|