FIR14-00815
| INSP-Sprinkler Rough-in/Hydro | 4/22/2015 | 4/22/2015 | 4/22/2015 1:46:36 PM | A | PART |
|
|
Begin 24 hr pneumatic test of new dry systems one and two at 10:00AM- System one @41.5psig System two at 43psig.
|
FIR14-00815
| INSP-Sprinkler Rough-in | 4/20/2015 | 4/22/2015 | 4/22/2015 1:39:49 PM | A | PART |
|
|
Completed remainder of overhead rough-in inspection for dry system one as noted on plan sheet FP25 and FP28. Corrections needed at units 412 and 413- sprinkler deflectors at some locations are too close to the deck per listing and obstructed by truss webs. Also verified previous C/N items for completion plan sheet FP28- units 400, 435, and 437.
|