Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE08-00342 ELE-Aging Inspection4/23/20094/23/20094/24/2009 4:24:25 PM DONE
no avtivity, see doc expire
ELE08-01532 ELE-Aging Inspection4/23/20094/23/20094/24/2009 3:44:53 PM DONE
suc, no activity
ESC09-00153 General Inspection4/23/20094/23/20094/23/2009 4:08:41 PMPPASS
looked ok
ELE09-00685 Electrical Rough-In4/23/20094/23/20094/23/2009 4:07:05 PMPPASS
Unerground and pole bases. Phone #: ###-#### Internet Inspection Request from: Todd Sellman met electrician, ok to cover u/g from transformer to last pole on south side lot
ELE09-00688 Conference4/22/20094/23/20094/23/2009 3:37:50 PMPDONE
Christina Phone #: ###-#### called am to advise that electrical contractor needs to do job, gave phone number for 412 and 324 to double check with, tried to call in pm, could only get number that sounded like fax answering machine, called 412 and said would respond as noted, no esc this project
ESC08-01037 General Inspection4/23/20094/23/20094/23/2009 3:19:18 PMPPASS
did not see sign, grass not planted, digging trench backyard, looked ok
ESC08-01016 General Inspection4/23/20094/23/20094/23/2009 3:11:52 PMPPASS
looked ok, sign down, but grass not yet planted
ELE09-00642 Final4/22/20094/23/20094/23/2009 3:04:14 PMPPASS
Inspector must call Jake about an hour before inspection so he can meet inspector at site. Phone #: ###-#### Internet Inspection Request from: Vicki Moore ok to final, no esc this project
ELE09-00679 Permanent Service4/23/20094/23/20094/23/2009 2:18:24 PMPPASS
Phone #: ###-#### Internet Inspection Request from: Lee VanSchoiack p/s u/g n ok, no esc this project
ELE09-00691 Permanent Service4/22/20094/23/20094/23/2009 1:16:31 PMPNR
New service inspection. Thank you, Eric Phone #: ###-#### Internet Inspection Request from: Eric Schroeder power company didn't cut power until late, electricians had to do lot more work than planned, no riser or grounding, plumbing in way at bottom of service, they eill call for am inspection, no esc this project, fee due
ELE09-00119 Final4/23/20094/23/20094/23/2009 9:56:42 AMAPASS
looked at sign, ok to final, no esc this project
ELE09-00681 Conference4/22/20094/23/20094/23/2009 9:47:32 AMADONE
Phil Phone #: ###-#### met contractor, reviewed service change, grounding, o/h clearance for future hot tub, no esc this project
ELE09-00270 Final4/23/20094/23/20094/23/2009 8:55:02 AMAFAIL
Code for garage door 1234.
Thanks! Phone #: ###-#### Internet Inspection Request from: Darryn Coburn called, left correction notice,NEC 210.63 shall provide receptacle within 25' of a/c
ELE09-00184 Final4/23/20094/23/20094/23/2009 8:32:05 AMAFAIL
Code for garage door 1234.
Thanks! Phone #: ###-#### Internet Inspection Request from: Darryn Coburn called, left correction notice, NEC 210.8(A)(6) kitchen countertop receptacles shall be gfci protected, 406.4(D) receptacle faces shall be flush with or project from faceplate (under island countertop),406.4 receptacles shall be securely mounted-front hall, upper north bedroom, Note- front lights dont work
ELE09-00475 Electrical Rough-In4/22/20094/23/20094/23/2009 7:19:04 AMAPART
This is for underground electrical conduit inspection in parking lot. Phone #: ###-#### Internet Inspection Request from: Daniel Gamboa ok to cover u/g anop, no esc this project