FIR09-00011
| FIR-Aging Inspection | 4/23/2009 | 4/23/2009 | 4/23/2009 4:32:12 PM | | DONE |
|
|
Need site inspection request.
|
FIR09-00008
| INSP-Final Inspection | 4/23/2009 | 4/23/2009 | 4/23/2009 4:22:09 PM | P | NR |
|
|
Scheduled by a contractor via Hello! on 4/23/2009 at 7:43:09 AM. Contact: ###-####.
|
FIR09-00008
| INSP-Supply line flush | 4/23/2009 | 4/23/2009 | 4/23/2009 4:21:09 PM | P | NR |
|
|
Pending coordination with united water for supply line flush.
|
FIR08-00624
| INSP-Final Inspection | 4/22/2009 | 4/23/2009 | 4/23/2009 3:17:03 PM | A | PASS |
|
|
Final inspection passed, one missing escutcheon installed while on site, permit finaled.
|
FIR09-00132
| INSP-Sprinkler Rough-in | 4/22/2009 | 4/23/2009 | 4/23/2009 2:51:01 PM | A | PART |
|
|
Overhead fire sprinkler system modifications per the scope of permit work are okay for cover at the drop ceilings, minor changes in field installation affecting final head location approved.
|
BLD06-02303
| FIRE-Final Inspection | 4/23/2009 | 4/23/2009 | 4/23/2009 2:48:50 PM | P | NR |
|
|
Building fire life safety cannot be approved until project related fire sprinkler and alarm permit work have passed final inspections. Note: Fire sprinkler failed dry system water delivery requirements at the 3rd and 4th level parking decks. Fire alarm system lacks interconnection to the exitsing structure sprinkler monitoring per conditions of the Temporary Occupancy agreement letter.
|
FIR08-00234
| INSP-Alarm Testing | 4/23/2009 | 4/23/2009 | 4/23/2009 2:37:55 PM | A | PART |
|
|
Testing completed for the remainder of the new elevator control devices including heat detectors at 3rd and 4th floors and elevator machine room, (damaged heat detector at the 4th floor replaced while on site), shunt trip and voltage monitoring, retested non-functional smoke detector at the 5th floor elevator lobby (replaced while on site), 9th floor flow switch retested, 5th 6th and 7th floor in duct detectors for fire smoke dampers, tested all smoke alarms at residential units on the 8th and 9th floors. NOTE: Need to provide sprinkler monitoring for the exisitng system at the adjacent parking structure per TOC agreement letter item #6/7, non-functional smoke alarm at unit 904, plans need to show accurate locations of devices at the basement, 1st and 18th floors (flow switch, tamper valves, SD and HD), post map at the fire command center, approved plans to reflect scope of work completed-new devices and interconnection to to systems at the adjacent building are not installed at this time, provide record of completion and inspection and testing reports.
|
FIR08-00018
| INSP-Sprinkler Rough-in/Hydro | 4/22/2009 | 4/23/2009 | 4/23/2009 1:53:38 PM | A | FAIL |
|
|
4th level parking garage dry system trip testing failed to meet requirements per NFPA 13 2007 7.2.3.2 thru 7.2.3.5. Dry system volume per approved plans is 752.22 gallons. 9th floor flow switch retested okay-adjustemnts to the PRV made while on site, noted sw head unit 706 is covered and missing escutcheon.
|