Inspections for the day of: Friday, April 23, 2010.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR10-00148 INSP-Final Inspection4/23/20104/23/20104/26/2010 6:26:49 AMPFAIL
Scott Phone #: ###-####. Inspection was for a rough to cover not a final inspection. Plan Mod required. Sprinkler spacing has been changed to 130 sf instead of the submitted 120 sf. The number of sprinklers on the branch lines changed. The pipe sizing was different from the approved plans. Hydraulics will be required to verify new spacing.
BLD07-01561 FIRE-Conference4/22/20104/23/20104/23/2010 1:33:39 PMADONE
I stopped at the job site and found that the restroom has been installed and stairs have been installed to the mezzanine both are lacking sprinkler protection. I spoke to Molli and Tammy about getting the permit finished.
FIR07-00848 INSP-Conference4/22/20104/23/20104/23/2010 12:13:36 PMADONE
I stopped at the job site and found that the restroom has been installed and stairs have been installed to the mezzanine both are lacking sprinkler protection. I spoke to Mike about getting the permit finished.
FIR09-00678 FIR-Aging Inspection4/23/20104/23/20104/23/2010 12:08:04 PM NR
I spoke to jason and he will try to schedule an inspection for next week
FIR09-00060 INSP-Final Inspection4/22/20104/23/20104/23/2010 11:28:01 AMAFAIL
Testing is complete and the pull stations functioned correctly. As-builts are needed since all but one of the manual pull stations shown to be relocated actually remained and is functional. The single pull station was shown to be relocated but was non-functional and was removed while I waited. Permit can be finaled when the as-builts are received.
FIR10-00018 INSP-Final Inspection4/22/20104/23/20104/23/2010 9:30:34 AMAFAIL
The forward flush of the backflow passed. This permit can be finaled when the interconnections with the fire alarm system have been verified. Ken to provide copies of the test papers at the next inspection.
BLD10-00418 FIRE-Final Inspection4/23/20104/23/20104/23/2010 9:28:55 AMPPASS
life safety passed
FIR09-00551 INSP-Final Inspection4/22/20104/23/20104/23/2010 9:23:39 AMPCANC
Per Greg there are problems that need to be corrected on the system and the inspection needs to be canceled and it will be rescheduled for next week.
FIR10-00135 INSP-Final Inspection4/22/20104/23/20104/23/2010 8:37:29 AMAFAIL
The city approved plans that had been left on the job site could not be found. No inspection was performed.
BLD10-00115 FIRE-Final Inspection4/22/20104/23/20104/23/2010 8:36:46 AMAFAIL
Several of the items noted by the plan reviewer to be addressed have not been performed yet so the inspection was going to be re-scheduled for next week. A full inspection was not performed. Also the project related fire sprinkler permit needs to be finaled as well.
FIR10-00014 INSP-Final Inspection4/22/20104/23/20104/23/2010 12:00:00 AMACANC
ken Phone #: ###-####