BLD06-02803
| BLD-Aging Inspection | 4/23/2015 | 4/23/2015 | 4/23/2015 3:54:35 PM | | PASS |
|
|
plm exp.// ele open
|
MIS15-00086
| Set Bond Amount | 4/23/2015 | 4/23/2015 | 4/23/2015 3:47:27 PM | P | DONE |
|
|
swo posted for lot clean up.
|
MIS15-00086
| Set Bond Amount | 4/23/2015 | 4/23/2015 | 4/23/2015 3:01:27 PM | P | DONE |
|
|
To set bond for clean up, home to be moved outside of city limits - Christina Phone #: ###-#### 8000.00
|
BLD15-00838
| BLD-Footing | 4/22/2015 | 4/23/2015 | 4/23/2015 2:39:09 PM | P | FAIL |
|
|
Dane Phone #: ###-####
|
BLD15-00316
| BLD-Framing/Rough-in | 4/21/2015 | 4/23/2015 | 4/23/2015 2:31:52 PM | P | PASS |
|
|
Call for access Phone #: 2083718924 >> Inspection requested via mobile web by Scott Larrondo
|
BLD14-00959
| BLD - Resubmittal Approved | 4/22/2015 | 4/23/2015 | 4/23/2015 2:14:04 PM | A | PASS |
|
|
Tim Phone #: ###-#### work in progress ok
|
BLD15-01052
| BLD-Foundation | 4/22/2015 | 4/23/2015 | 4/23/2015 1:47:08 PM | P | PASS |
|
|
Pouring at 1 - Wes Phone #: ###-####
|
BLD15-01020
| BLD-Footing | 4/22/2015 | 4/23/2015 | 4/23/2015 1:46:46 PM | P | FAIL |
|
|
Dane Phone #: ###-#### no exavation
|
BLD13-00181
| BLD-Ceiling Grid Inspection | 4/22/2015 | 4/23/2015 | 4/23/2015 11:22:46 AM | A | PASS |
|
|
1st and 2nd floor wind a b and c // JC Phone #: ###-####
|
BLD15-01143
| BLD-Framing/Rough-in | 4/22/2015 | 4/23/2015 | 4/23/2015 10:38:57 AM | A | PASS |
|
|
Shane Phone #: ###-####
|
BLD13-02423
| BLD-Framing/Rough-in | 4/22/2015 | 4/23/2015 | 4/23/2015 10:08:22 AM | A | PASS |
|
|
level 1 steel stud wall ; ceiling framing for drywall cover Phone #: ###-#### Inspection requested via web by Mike Wilson 3 floor exterior walls ok
|
BLD13-02425
| BLD-Energy code compliance | 4/22/2015 | 4/23/2015 | 4/23/2015 10:06:34 AM | A | PASS |
|
|
level 2 shower pan grouting in PT deck, Exterior insulation in perimeter walls Phone #: ###-#### Inspection requested via web by Mike Wilson
|