FIR14-00529
| INSP-Sprinkler Rough-in | 4/20/2015 | 4/23/2015 | 4/24/2015 2:13:24 PM | A | PART |
|
|
Hydrostatic test on all four risers in new warehouse satisfactory completed.
|
FIR39-00005
| INSP-Sprinkler Rough-in/Hydro | 4/23/2015 | 4/23/2015 | 4/24/2015 8:23:57 AM | A | PASS |
|
|
|
BLD14-02599
| FIRE-Final Inspection | 4/23/2015 | 4/23/2015 | 4/23/2015 3:13:50 PM | P | PASS |
|
|
Fire Life Safety pass. One exit sign at interior entrance to new room to be repaired (batteries) prior to final bldg inspection.
|
FIR15-00108
| INSP-Final Inspection | 4/22/2015 | 4/23/2015 | 4/23/2015 2:45:05 PM | P | FAIL |
|
|
Two notification devices need to be adjusted to meet code. Three in duct spot detectors and duct detectors were tested, verified acceptable damper closure and fan shut down. Notification not tested.
|
FIR14-00815
| INSP-Sprinkler Rough-in/Hydro | 4/22/2015 | 4/23/2015 | 4/23/2015 11:31:35 AM | A | PART |
|
|
24 hr air test for dry systems 1 and 2 completed satisfactory. End pressures recorded, system one 40.5 psig, system two 43 psig. Completed rough-in for dry system 3 on fourth floor. Correction items are as follows straighten on two heads in rm 424, and one head each in rms 426 and 423. RM 420 has two obstructed heads to be relocated and 2 missing hangars. Rm 414 has a head located under vent to be moved to side. Previous C/N items were not able to be corrected due to pressure system, to be verified at next inspection.
|
BLD15-00395
| FIRE-Final Inspection | 4/22/2015 | 4/23/2015 | 4/23/2015 11:26:54 AM | A | PASS |
|
|
Life Safety pass. Verified all extinguisher and hood suppression system are current on annual inspections.
|
BLD14-00936
| FIRE-Final Inspection | 4/22/2015 | 4/23/2015 | 4/23/2015 9:46:27 AM | A | PASS |
|
|
Life Safety Pass. Verified new bathroom hardware exceptable.
|