ELE08-00263
| Conference | 4/24/2008 | 4/24/2008 | 4/24/2008 4:47:33 PM | P | DONE |
|
|
adam Phone #: ###-#### . .1. talked about service for the building. . .
|
ELE08-00952
| Conference | 4/24/2008 | 4/24/2008 | 4/24/2008 4:11:09 PM | P | NH |
|
|
jack Phone #: ###-#### . .1. not home for confrence. . .
|
ELE07-04073
| Permanent Service | 4/23/2008 | 4/24/2008 | 4/24/2008 3:42:08 PM | P | PASS |
|
|
We need an early aft inspection, so that Idaho Power can pull new wire and rehook up power. Thanks. Phone #: ###-#### Internet Inspection Request from: Barbara Szurgot . .1. p/s u/g reconnect ok. . .
|
ELE07-04073
| Electrical Rough-In | 4/24/2008 | 4/24/2008 | 4/24/2008 3:35:47 PM | P | PASS |
|
|
We need an early aft inspection, so that Idaho Power can pull new wire and rehook up power. Thanks. Phone #: ###-#### Internet Inspection Request from: Barbara Szurgot . .1. conduit burial ok between buildings. . .
|
ELE08-00577
| Final | 4/23/2008 | 4/24/2008 | 4/24/2008 12:47:35 PM | A | PASS |
|
|
home owner will be there Phone #: ###-#### Internet Inspection Request from: Joe Thomas . .1. final ok. . .
|
ELE08-00401
| Final | 4/22/2008 | 4/24/2008 | 4/24/2008 11:43:20 AM | A | PASS |
|
|
Tool install at Bldg 80. SUP05. 7072161 Phone #: ###-#### Internet Inspection Request from: Ken Heller . .1. final ok. . .
|
ELE08-00747
| Final | 4/21/2008 | 4/24/2008 | 4/24/2008 10:02:43 AM | A | PASS |
|
|
Mike, this is a clean room tool in Fab 4. Phone #: ###-#### Internet Inspection Request from: Eric Landberg . .1. final ok. . .
|
ELE08-00735
| Final | 4/21/2008 | 4/24/2008 | 4/24/2008 8:57:41 AM | A | PASS |
|
|
Mike, this is a clean room tool in Fab 4. Phone #: ###-#### Internet Inspection Request from: Eric Landberg . .1. final ok. . .
|