BLD13-00844
| FIRE-Final Inspection | 4/24/2013 | 4/24/2013 | 4/26/2013 4:26:33 PM | P | PASS |
|
|
Inspection passed per 430 on 4/19
|
BLD12-01128
| FIRE-Final Inspection | 4/24/2013 | 4/24/2013 | 4/26/2013 4:25:39 PM | P | PASS |
|
|
Fire life safety passed pending door hardware revision at the new restroom.
|
BLD13-00884
| FIRE-Conference | 4/24/2013 | 4/24/2013 | 4/26/2013 4:24:27 PM | P | DONE |
|
|
On site conference with contractor regarding existing fire sprinkler system and remodel work.
|
BLD13-00917
| FIRE-Final Inspection | 4/23/2013 | 4/24/2013 | 4/25/2013 7:15:29 AM | P | PASS |
|
|
Life safety inspection completed satisfactory.
|
FIR13-00057
| INSP-Final Inspection | 4/24/2013 | 4/24/2013 | 4/24/2013 2:35:14 PM | A | PART |
|
|
"Phase one" work completed satisfactory.
|
BLD13-00755
| FIRE-Final Inspection | 4/24/2013 | 4/24/2013 | 4/24/2013 2:31:29 PM | P | PASS |
|
|
Previous correction items verified for completion. Fire life safety passed.
|
BLD13-00004
| FIRE-Conference | 4/23/2013 | 4/24/2013 | 4/24/2013 2:29:28 PM | A | DONE |
|
|
On site discussion with contractor regarding life safety issues including exit signs, EM lights, PFE's.
|
BLD13-00535
| FIRE-Final Inspection | 4/23/2013 | 4/24/2013 | 4/24/2013 2:27:21 PM | A | FAIL |
|
|
Missing approved plans on site, post fire extinguisher as discussed, remove manual thumbturn at the main entry/exit, post "door to remain..." signage at the main entry.
|
BLD13-00293
| FIRE-Sprinkler Rough-in | 4/24/2013 | 4/24/2013 | 4/24/2013 2:25:21 PM | A | PART |
|
|
Overhead fire sprinkler work is approved for cover at the grid ceilings.
|
FIR12-00252
| INSP-Conference | 4/24/2013 | 4/24/2013 | 4/24/2013 2:24:17 PM | A | DONE |
|
|
Michael phone #: ###-####
|