ESC14-00588
| Site Preparation | 4/24/2015 | 4/24/2015 | 4/24/2015 4:09:59 PM | P | PEND |
|
|
Site walk through to occur next week. Perimeter BMPs, construction fencing, and silt fence along creek channel have been installed. Some minor site grubbing/exploration has occured. No issues at site. Will check back next week.
|
ESC13-01231
| BMP Violation | 4/24/2015 | 4/24/2015 | 4/24/2015 3:38:40 PM | P | PASS |
|
|
Wednesday inspection observed spilled gypcrete mix that was not fully cleaned.
Correction request to ESC to clean Dale Street has now been completed. Superior Interiors (gypcrete contractor) cleaned up spill Thursday morning. ESI then has streets swept and resinstalled fencing/wattles along Dale.
Approved. Very quality corrective action and beat this mornings rainfall.
|
ESC13-00193
| General Inspection | 4/24/2015 | 4/24/2015 | 4/24/2015 3:19:25 PM | | PART |
|
|
No vertical construction occuring yet. Hillsides staying stable. Perimeter BMPs are installed and containing sediment.
Correction:
Need to clean DI bag and accumulated sediment around the stormdrain on Crestline @ Boise Hills.
|
ESC11-00192
| General Inspection | 4/24/2015 | 4/24/2015 | 4/24/2015 3:13:23 PM | | PASS |
|
|
|
ESC13-01167
| General Inspection | 4/24/2015 | 4/24/2015 | 4/24/2015 2:25:40 PM | | PASS |
|
|
Back hillside has been recently hydroseeded/tackified in addition to the placement of large boulders. BLD already finaled. Will wait for the hillside vegetation to establish.
|
ESC14-00477
| General Inspection | 4/22/2015 | 4/24/2015 | 4/24/2015 12:48:58 PM | P | PASS |
|
|
39th Street Village is near full completion. 2 lots are not yet stabilized. No trackout or turbid discharges.
Hayden Homes or McMaster will need to conduct a final sweeping along 39th before ESC final.
No corrective actions needed at this time.
|
ESC14-00865
| General Inspection | 4/23/2015 | 4/24/2015 | 4/24/2015 12:06:33 PM | A | PASS |
|
|
Spectrum facade renovation and central square brick/paver project is in progress. Permit posted on security fence on south end of project. No trackout or discharges. Perimeter wattles installed and lined concrete washout pit has been provided.
Approved.
|
ESC13-01323
| General Inspection | 4/24/2015 | 4/24/2015 | 4/24/2015 11:36:05 AM | P | PASS |
|
|
Cantabria subdivsion of 4 -plexes is in progress. Site perimeter is clean. A new lined concrete washout pit was provided as requested during last inspection. All receiving storm drains (private & MS4) have sediment protection. No violations observed.
Note - closed ESC permits for buildings #1-5 (ESC13-001324 to ESC13-001329)
|
ESC13-01327
| DOC - Permit Finaled | 4/24/2015 | 4/24/2015 | 4/24/2015 11:32:58 AM | P | PASS |
|
|
|
ESC13-01325
| DOC - Permit Finaled | 4/24/2015 | 4/24/2015 | 4/24/2015 11:32:42 AM | P | PASS |
|
|
|
ESC13-01324
| Aging Inspection | 4/24/2015 | 4/24/2015 | 4/24/2015 11:31:58 AM | | PASS |
|
|
Earthwork for Cantabria 4-plex foundation complete. Frame is up. Cantabria subdivision BMPs include silt fence along Ridenbaugh Canal, MS4 inlet protection, DI bags on private storm drains. Access road has been paved. No trackout to Overland or Cloverdale.
ESC inspections to be covered under main development ESC permit ESC13-01323. Closed buildings #15 (-01324 to - 01329) to reduce inspection frequency at this site. ESC permit conditions still apply.
|
ESC13-01324
| DOC - Permit Finaled | 4/24/2015 | 4/24/2015 | 4/24/2015 11:31:49 AM | P | PASS |
|
|
|
ESC13-01325
| Aging Inspection | 4/24/2015 | 4/24/2015 | 4/24/2015 11:31:40 AM | | PASS |
|
|
Earthwork for Cantabria 4-plex foundation complete. Frame is up. Cantabria subdivision BMPs include silt fence along Ridenbaugh Canal, MS4 inlet protection, DI bags on private storm drains. Access road has been paved. No trackout to Overland or Cloverdale.
ESC inspections to be covered under main development ESC permit ESC13-01323. Closed buildings #15 (-01324 to - 01329) to reduce inspection frequency at this site. ESC permit conditions still apply.
|
ESC13-01326
| Aging Inspection | 4/24/2015 | 4/24/2015 | 4/24/2015 11:31:27 AM | | PASS |
|
|
Earthwork for Cantabria 4-plex foundation complete. Frame is up. Cantabria subdivision BMPs include silt fence along Ridenbaugh Canal, MS4 inlet protection, DI bags on private storm drains. Access road has been paved. No trackout to Overland or Cloverdale.
ESC inspections to be covered under main development ESC permit ESC13-01323. Closed buildings #15 (-01324 to - 01329) to reduce inspection frequency at this site. ESC permit conditions still apply.
|
ESC13-01326
| DOC - Permit Finaled | 4/24/2015 | 4/24/2015 | 4/24/2015 11:31:18 AM | P | PASS |
|
|
|
ESC13-01327
| Aging Inspection | 4/24/2015 | 4/24/2015 | 4/24/2015 11:31:08 AM | | PASS |
|
|
Earthwork for Cantabria 4-plex foundation complete. Frame is up. Cantabria subdivision BMPs include silt fence along Ridenbaugh Canal, MS4 inlet protection, DI bags on private storm drains. Access road has been paved. No trackout to Overland or Cloverdale.
ESC inspections to be covered under main development ESC permit ESC13-01323. Closed buildings #15 (-01324 to - 01329) to reduce inspection frequency at this site. ESC permit conditions still apply.
|
ESC13-01329
| Aging Inspection | 4/24/2015 | 4/24/2015 | 4/24/2015 11:30:52 AM | | PASS |
|
|
Earthwork for Cantabria 4-plex foundation complete. Frame is up. Cantabria subdivision BMPs include silt fence along Ridenbaugh Canal, MS4 inlet protection, DI bags on private storm drains. Access road has been paved. No trackout to Overland or Cloverdale.
ESC inspections to be covered under main development ESC permit ESC13-01323. Closed buildings #15 (-01324 to - 01329) to reduce inspection frequency at this site. ESC permit conditions still apply.
|
ESC13-01329
| DOC - Permit Finaled | 4/24/2015 | 4/24/2015 | 4/24/2015 11:30:42 AM | P | PASS |
|
|
|
ESC14-00657
| General Inspection | 4/24/2015 | 4/24/2015 | 4/24/2015 10:53:46 AM | P | PASS |
|
|
RH #6 has all roads and utilities installed. Rock Placing company installing a rock retaining wall on the lots abutting the foothills.
No hillside erosion occuring, no trackout, no turbid discharges. Individual lots will begin later this summer it appears.
|
ESC13-00230
| General Inspection | 4/24/2015 | 4/24/2015 | 4/24/2015 10:38:43 AM | | PASS |
|
|
Streets, gutters, and storm drain inlets do not have any sediment accumulations. No trackout from sites. Lined washout and DI bags have remaining capacity. RH#5 is over 70% full. No corrections at this time. Site still being inspected by Brighton RP for CGP compliance.
|
ESC15-00338
| Random Inspection | 4/24/2015 | 4/24/2015 | 4/24/2015 10:10:20 AM | P | PASS |
|
|
Site foundation half basement have been excavated. Stockpiles temporarily stored within grassy perimeter. No sediment runoff occuring. Street and sidewalk have been swept after excavation. No trackout. Permit posted, porta pot staked down.
|
ESC15-00326
| DOC - Permit Finaled | 4/24/2015 | 4/24/2015 | 4/24/2015 10:08:22 AM | P | PASS |
|
|
Demo complete. Site cleaned and is now a new SFH in progress. No issues. See ESC15-00338.
|
ESC15-00288
| Site Preparation | 4/23/2015 | 4/24/2015 | 4/24/2015 10:02:18 AM | A | PASS |
|
|
Rusty Phone #: ###-####
RP/GC onsite. Flat infill with 3 "skinny" lots. Plan is to preserve grass strip along Euclid as long as possible and access through the alley (gravel). Once grass is removed, a sediment capture BMP should be used in gutter north (slight slope) of site. Note - DI is irregular shape so filter bag wont work.
Permit posted on back tree. Cleared Rusty to start adjacent lots when ready since all are connected.
|
ESC13-00213
| General Inspection | 4/24/2015 | 4/24/2015 | 4/24/2015 9:07:53 AM | | PASS |
|
|
No construction activity. Status of permits still on hold. No turbid discharges from site. Hillsides have vegetation (weeds/cheat grass) that are helping secure sediment.
|
ESC15-00520
| Site Preparation | 4/23/2015 | 4/24/2015 | 4/24/2015 8:49:08 AM | A | PASS |
|
|
Brayden Phone #: ###-####
Small residential addition in backyard. RP-GC on site, the lawn area provides natural sediment containment. Flat lot/low ESC risk. Approved.
|
ESC14-00865
| Site Preparation | 4/23/2015 | 4/24/2015 | 4/23/2015 4:11:01 PM | A | CANC |
|
|
data entry error
|