BLD16-01092
| FIRE-Final Inspection | 4/21/2017 | 4/24/2017 | 4/24/2017 2:45:45 PM | P | FAIL |
|
|
I went over life safety requirements with the project superintendant since alarms and sprinkler permits were not ready. There is a short list of corrections marked in red on the Fire Review Notes.
|
FIR16-00588
| INSP-Final Inspection | 4/21/2017 | 4/24/2017 | 4/24/2017 2:44:21 PM | P | CANC |
|
|
Water was not turned on yet. I spoke to George about my previous concerns with lack of protection in the room at the bottom of the brass pole.
|
FIR16-00454
| INSP-Final Inspection | 4/21/2017 | 4/24/2017 | 4/24/2017 2:41:08 PM | P | CANC |
|
|
No fire alarm test due to the sprinkler contractor not having water turned on and elevator guy was not there.
|
BLD14-02837
| FIRE-Final Inspection | 4/21/2017 | 4/24/2017 | 4/24/2017 7:51:27 AM | A | PART |
|
|
Life safety for Phase II passed.
Lee Phone #: ###-####
|