Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD16-01092 FIRE-Final Inspection4/21/20174/24/20174/24/2017 2:45:45 PMPFAIL
I went over life safety requirements with the project superintendant since alarms and sprinkler permits were not ready. There is a short list of corrections marked in red on the Fire Review Notes.
FIR16-00588 INSP-Final Inspection4/21/20174/24/20174/24/2017 2:44:21 PMPCANC
Water was not turned on yet. I spoke to George about my previous concerns with lack of protection in the room at the bottom of the brass pole.
FIR16-00454 INSP-Final Inspection4/21/20174/24/20174/24/2017 2:41:08 PMPCANC
No fire alarm test due to the sprinkler contractor not having water turned on and elevator guy was not there.
BLD14-02837 FIRE-Final Inspection4/21/20174/24/20174/24/2017 7:51:27 AMAPART
Life safety for Phase II passed.

Lee Phone #: ###-####