BLD03-01845
| FIRE-Final Inspection | 4/24/2006 | 4/24/2006 | | A | |
|
|
For final status
|
BLD05-03448
| FIRE-Final Inspection | 4/24/2006 | 4/25/2006 | 4/26/2006 8:20:34 AM | P | FAIL |
|
|
Several issues need addressed as discussed on site regarding life safety inspection for the basement only including door hardware (knobs at stairway exits, manual flush bolts on inactive leafs, padlocks on cooler and storage rooms, missing closures and seals at rated room doors, etc.), exit signs at some areas are not illuminated or need relocation, fire extinguishers shall be mounted no higher than 48" AFF, some locations may be overspaced to the nearest FE (75' max travel), provide max occupant load sign for the meeting room, need to test emergency lighting for the path of egress, access controlled egress doors shall be tested for loss of power and alarm at the mag locks, provide smoke detection for the battery room (a HD appears to be installed), one 200 deg. QR head needs replaced as noted, per the upgrade agreement some required alarm and sprinkler issues related to the basement are not completed at this time. Not all items reviewed at this inspection, contractor to re-schedule when general noted issues have been corrected.
|
FIR05-00449
| INSP-Alarm Testing | 4/25/2006 | 4/25/2006 | 4/26/2006 7:52:34 AM | P | DEFR |
|
|
Inspection to be scheduled 4/27 per agreement.
|
FIR06-00128
| INSP-Sprinkler Rough-in/Hydro | 4/24/2006 | 4/25/2006 | 4/26/2006 7:51:28 AM | P | PART |
|
|
Completed cover inspection for the 4" feed main inside wall through floor from basement to the 1st floor overhead system, okay to cover as marked on plans.
|
FIR06-00268
| INSP-Sprinkler Rough-in/Hydro | 4/25/2006 | 4/25/2006 | 4/25/2006 1:52:26 PM | P | PART |
|
|
Overhead work is good for cover at the drop ceiling, final pending ceiling tile and escutcheon installation, will also need to verify riser is tagged with a current annual inspection for the existing system.
|
FIR05-00689
| INSP-Final Inspection | 4/24/2006 | 4/25/2006 | 4/25/2006 11:40:52 AM | A | PASS |
|
|
Fire sprinkler shell permit has been finaled, TI permit is now acceptable for final.
|
FIR05-00742
| INSP-Final Inspection | 4/24/2006 | 4/25/2006 | 4/25/2006 10:25:57 AM | A | PASS |
|
|
The required corrections have been made, the project related shell sprinkler permit is complete, inspection passed, permit finaled.
|
FIR05-00741
| INSP-Final Inspection | 4/24/2006 | 4/25/2006 | 4/25/2006 10:20:13 AM | A | PASS |
|
|
Fire sprinkler work passed inspection, the related shell sprinkler permit has been completed, permit finaled.
|
BLD06-00962
| FIRE-Final Inspection | 4/24/2006 | 4/25/2006 | 4/25/2006 10:08:14 AM | A | FAIL |
|
|
renee ###-#### fire spr check Fire sprinklers in the hallway adjacent to the remodeled area are overspaced and missing at some locations. Work to correct these issues will require a fire sprinkler permit.
|
FIR05-00742
| INSP-Final Inspection | 4/24/2006 | 4/25/2006 | 4/24/2006 2:55:54 PM | A | CANC |
|
|
Contact - Final for Funkiton TI; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
|