Inspections for the day of: Tuesday, April 25, 2006.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR05-00693 INSP-Sprinkler Rough-in/Hydro4/25/20064/25/20064/25/2006 4:31:47 PMPPASS
The sprinkler piping located above the hard lid ceilings is ok to cover. Exact locations are marked on the approved plans.
FIR05-00582 INSP-Sprinkler Rough-in/Hydro4/25/20064/25/20064/25/2006 4:31:12 PMPPASS
The sprinkler piping located above the hard lid ceilings is ok to cover. Exact locations are marked on the approved plans.
FIR06-00239 INSP-Sprinkler Rough-in4/25/20064/25/20064/25/2006 4:29:59 PMPPASS
The underground supply is ok to cover. The routing of the piping has been changed. Instead of supplied from the south side of the driveway it is now tied into the north side. One less 45 elbow has been used but distance is farther. This change needs to be reflected on the overhead submittals. Also the contractor needs to receive fire dept approval for running the piping under the utility pad and possible placement of the fire dept connection.
FIR05-00604 INSP-Sprinkler Rough-in/Hydro4/25/20064/25/20064/25/2006 2:36:02 PMPFAIL
Above ground hydro test failed. I counted six leaks on the floor. I requested that the sprinkler system gets tested before I inspect to save time.
FIR05-00586 INSP-Sprinkler Rough-in/Hydro4/24/20064/25/20064/25/2006 12:45:53 PMPPART
24 Hr Air Test started at 12:35 with 44 1/2psi showing on the guage.
FIR06-00168 INSP-Sprinkler Rough-in/Hydro4/24/20064/25/20064/25/2006 10:24:04 AMAPART
This was a partial inspection of the underground. The 6" supply piping from the riser to the first 45 elbow is ok to cover. Per Dave with DeBest the piping will be at 4'-6" below grade even though it is not now. The grade will need to be atleast 3" above the bottom of the tilt up wall that passes over the piping.