FIR17-00643
| INSP-Sprinkler Rough-in/Hydro | 4/24/2018 | 4/25/2018 | 4/25/2018 1:27:59 PM | A | DONE |
|
|
Hydrostatic test for underground supply witnessed, no pressure loss observed at contractor provided gauge.
|
FIR17-00669
| INSP-Sprinkler Rough-in/Hydro | 4/24/2018 | 4/25/2018 | 4/25/2018 1:27:43 PM | A | DONE |
|
|
Hydrostatic test for underground supply witnessed, no pressure loss observed at contractor provided gauge.
|
FIR17-00643
| INSP-Supply line flush | 4/24/2018 | 4/25/2018 | 4/25/2018 11:27:39 AM | A | DONE |
|
|
Underground supply flush complete.
|
FIR17-00669
| INSP-Supply line flush | 4/24/2018 | 4/25/2018 | 4/25/2018 11:27:21 AM | A | DONE |
|
|
Underground supply flush complete.
|
FIR17-00286
| INSP-Sprinkler Rough-in | 4/24/2018 | 4/25/2018 | 4/25/2018 11:26:42 AM | A | PASS |
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, area of work approved for cover.
|
FIR18-00299
| INSP-Sprinkler Rough-in | 4/24/2018 | 4/25/2018 | 4/25/2018 11:23:16 AM | A | PART |
|
|
Rough to cover inspection for overhead fire sprinkler piping above hardlids complete, notated city approved drawings with red ink areas approved for cover.
|