FIR17-00689
| INSP-Sprinkler Rough-in | 4/25/2018 | 4/26/2018 | 4/26/2018 2:22:53 PM | P | PART |
|
|
Rough to cover inspection for overhead fire sprinkler piping complete, all hardlids approved for cover, fire sprinkler heads that will be installed in drop in tile ceiling will need to be inspected before cover is approved.
|
FIR17-00232
| INSP-Final Inspection | 4/23/2018 | 4/26/2018 | 4/26/2018 12:40:07 PM | A | PASS |
|
|
Final fire alarm inspection complete.
|
FIR16-00586
| INSP-Final Inspection | 4/24/2018 | 4/26/2018 | 4/26/2018 12:39:45 PM | A | PASS |
|
|
Final fire sprinkler inspection complete.
|
FIR16-00586
| INSP-Sprinkler Rough-in/Hydro | 4/24/2018 | 4/26/2018 | 4/26/2018 12:39:23 PM | A | DONE |
|
|
Hydrostatic test for levl 4 wet system witnessed, no pressure loss observed at rised provided gauge.
|
FIR18-00191
| INSP-Sprinkler Rough-in | 4/25/2018 | 4/26/2018 | 4/26/2018 10:40:56 AM | A | PASS |
|
|
Rough to cover inspection for overhead fire sprinkler piping complete, approved for cover.
|
FIR18-00024
| INSP-Sprinkler Rough-in | 4/25/2018 | 4/26/2018 | 4/26/2018 9:21:44 AM | A | CANC |
|
|
Tried calling point of contact multiple times, call went straight to voicemail, could not locate city approved drawings to make notations, inspection will need to be rescheduled, this request is cancelled.
Jeff Chaney is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR17-00763
| INSP-Sprinkler Rough-in | 4/25/2018 | 4/26/2018 | 4/26/2018 8:48:12 AM | A | PASS |
|
|
Rough to cover inspection for overhead fire sprinkler piping in breakroom addition complete, approved for cover.
|
BLD18-00154
| FIRE-Final Inspection | 4/26/2018 | 4/26/2018 | 4/26/2018 8:36:59 AM | A | PASS |
|
|
Final fire sprinkler inspection complete, final fire alarm inspection complete, fire extinguishers are in common areas with current inspection tags. Final life fire safety inspection for area of work complete.
|