FIR14-00815
| INSP-Sprinkler Rough-in | 4/23/2015 | 4/27/2015 | 4/27/2015 10:57:31 AM | A | PART |
|
|
Tenting inspection complete at 4th floor, section 1. Noted that a barrier should be placed between exhaust fan piping to exterior and sprinkler piping where they share inter-joist space. Rm 441 especially. Corrections were being made on spot.
|
FIR13-00725
| INSP-Sprinkler Rough-in | 4/24/2015 | 4/27/2015 | 4/27/2015 9:39:32 AM | A | PART |
|
|
Dry pipe stub ups for FDC and Test header off of myrtle street ok to be wrapped and covered.
|
FIR14-00069
| INSP-Conference | 4/24/2015 | 4/27/2015 | 4/27/2015 8:14:09 AM | A | DONE |
|
|
TOB Bldg. J - Underground. Phone conference complete. Verified that underground fire line must be able to hold 200 psig. General contractor installed up to PIV and only holds 130 psig currently.
|