Inspections for the day of: Wednesday, April 27, 2016.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRock A. Hudson
TitleELE-INSPECTOR
Phone #794-6794
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE13-02418 ELE-Aging Inspection4/27/20164/27/20164/29/2016 4:17:13 PM CANC
ELE13-02038 ELE-Aging Inspection4/27/20164/27/20164/29/2016 4:16:43 PM CANC
ELE16-00660 Final4/27/20164/27/20164/27/2016 3:35:58 PMPPASS
Dan Phone #: ###-#### Final ok
ELE16-00336 Final4/27/20164/27/20164/27/2016 3:26:50 PMPPASS
Phone #: ###-#### Inspection requested via web by Greg Thomas
Final ok
ELE16-01321 Electrical Rough-In4/27/20164/27/20164/27/2016 2:29:01 PMPPASS
Rewired the kitchen. Call before you go. Thanks, Greg Phone #: ###-#### Inspection requested via web by Greg Idsinga
Questioned existing switching system of house and contractor informed it is all low voltage system to remain. Kitchen remodel rough in ok cover
ELE16-01305 Final4/27/20164/27/20164/27/2016 1:47:10 PMPFAIL
Inspection requested via web by Matthew White
250.28- Main bonding jumper shall be installed on existing main breaker panel. 250.53(D)(2)- underground water pipe shall have supplemental rod installed.
Approved P/S to occupied with corrections to be completed for final.
ELE16-01305 Permanent Service4/27/20164/27/20164/27/2016 1:46:34 PMPPASS
Inspection requested via web by Matthew White p/s o/h rec ok
ELE16-01330 Rough-In Permanent Service4/26/20164/27/20164/27/2016 1:27:28 PMPCANC
late in day please! Ok for Id power to restore power Phone #: ###-#### Inspection requested via web by Randy Fletcher Needed conference
ELE16-01330 Conference4/27/20164/27/20164/27/2016 1:27:17 PMPDONE
late in day please! Ok for Id power to restore power Phone #: ###-#### Inspection requested via web by Randy Fletcher
Discussed location of metermain under existing deck where walls have been built to enclose under deck area. Checked with Daryl Degrange and determined that area not concidered as interior or part of structure. Underground service entrance to be installed in sch 80 PVC 3 1/2' verticle to metermain than fused there is acceptable. Contractor to change dryer and range receptacles to 4 wire and bond plumbing at water heater and install a ground rod to supplement.
ELE16-01235 Final4/26/20164/27/20164/27/2016 12:36:12 PMAPASS
Approved plans onsite. Please call Ryan King with any questions. ###-#### Phone #: ###-#### Inspection requested via web by Ryan King
Final ok
ELE16-01326 Final4/26/20164/27/20164/27/2016 10:47:45 AMAFAIL
Robert Phone #: ###-####
110.26- Work clearance for service pedistal shall be 36" deep and 30" wide shall be maintained. The addition of heat pump placed 18" in front of pedistal is in this space.
ELE16-01319 Electrical Rough-In4/27/20164/27/20164/27/2016 10:01:54 AMAPASS
Cal, gate beside garage is open walk to back yard. Phone #: ###-#### Inspection requested via web by cal crosby
Garage addition rough in ok cover
ELE16-01292 Temporary Service4/26/20164/27/20164/27/2016 9:01:35 AMAPASS
Phone #: ###-#### Inspection requested via web by Darryn Coburn
t/s u/g n ok
ELE15-01035 Final4/27/20164/27/20164/27/2016 8:47:50 AMAPASS
garage code 0813 Phone #: ###-#### Inspection requested via web by cal crosby Final ok