ELE19-02894
| Electrical Rough-In | 4/27/2020 | 4/27/2020 | 4/27/2020 3:47:59 PM | P | DONE |
|
|
ok with video/photo // larry Phone #: ###-####...occupied home with homeowner doing work...discussed with him COVID19 inspection protocals...non essential work...inspection will be done by pics sent thru email...waiting on email..follow up inspection scheduled for next day
|
ELE20-01368
| Final | 4/24/2020 | 4/27/2020 | 4/27/2020 3:23:57 PM | P | PASS |
|
|
crew will be ready in afternoon after 1pm for final ###-#### Phone #: ###-#### Inspection requested via web by Terissa Morain... labelling, disconnect, and OCPD ok
|
ELE20-01186
| Permanent Service | 4/27/2020 | 4/27/2020 | 4/27/2020 2:55:09 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by jamie berg.... correction made uffer connection shall be accessible at final p/s u/g new ok...back of property
|
ELE19-03961
| Electrical Rough-In | 4/26/2020 | 4/27/2020 | 4/27/2020 1:49:45 PM | P | PASS |
|
|
3rd floor units Phone #: ###-#### Inspection requested via web by Todd Hall... 3rd floor units and breezeway up to heat tape junction box ok to cover
|
ELE19-04581
| Final | 4/27/2020 | 4/27/2020 | 4/27/2020 1:11:42 PM | P | PART |
|
|
Phone #: ###-#### Inspection requested via web by Brad Girard... temp occupency given...remaining labelling of panels and HVAC units, misc thru out building, service ground protection, and all equipment for UL verification,circuitry, breaker size
|
ELE20-01398
| Electrical Rough-In | 4/24/2020 | 4/27/2020 | 4/27/2020 12:25:21 PM | P | FAIL |
|
|
ready for electrical ground work inspection crew will be back onsite in the afternoon Phone #: ###-#### Inspection requested via web by Terissa Morain... 1) trench shall be a minimum 18" deep to top of pipe...2 open ends not deep enough...require mid point opened up to verify depth
|
ELE20-01400
| Electrical Rough-In | 4/23/2020 | 4/27/2020 | 4/27/2020 11:42:11 AM | A | FAIL |
|
|
Please call Roger for access information prior to arrival. Secured area of access. Phone #: ###-#### Inspection requested via web by Kevin Perez...no access...called contact number multiple times...no answer
|
ELE20-01447
| Temporary Service | 4/27/2020 | 4/27/2020 | 4/27/2020 11:30:36 AM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Dan Rohl...t/s u/g new ok
|
ELE20-00918
| Final | 4/27/2020 | 4/27/2020 | 4/27/2020 11:14:51 AM | P | PASS |
|
|
Mike Phone #: ###-####...ok to final
|
ELE20-01064
| Final | 4/27/2020 | 4/27/2020 | 4/27/2020 10:26:34 AM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Greg Idsinga...job complete..ok to final
|
ELE20-01088
| Electrical Rough-In | 4/27/2020 | 4/27/2020 | 4/27/2020 10:00:21 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Scott Campbell...interior ceiling drops for cans x 3 areas...cans will be cut in after sheetrock installed
|
ELE19-04181
| Electrical Rough-In | 4/26/2020 | 4/27/2020 | 4/27/2020 9:39:13 AM | A | PASS |
|
|
Give me a call when you arrive. I will be on site thanks, Ron Phone #: ###-#### Inspection requested via web by Ron Zimmerman... new ceiling grid...several areas ok to cover...areas given on tag...E hallway, men's bath, breakroom, electrical rm office, locker room, front entry...
|
ELE19-04181
| Electrical Rough-In | 4/27/2020 | 4/27/2020 | 4/27/2020 9:37:18 AM | A | FAIL |
|
|
Give me a call when you arrive. I will be on site thanks, Ron Phone #: ###-#### Inspection requested via web by Ron Zimmerman...
correction notice given 1) all data cabling, fire alarm wiring, and any low voltage wiring will be support and not laying on grid 2) S/O cord being used as permanent wiring shall be removed...S/O not rated for permanent wiring or used above grid
|
ELE20-01424
| Rough-In Permanent Service | 4/25/2020 | 4/27/2020 | 4/27/2020 8:56:45 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Troy Ballard... rough ok to cover p/s u/g new ok
|
MIS20-00131
| ELE-Conference | 4/24/2020 | 4/27/2020 | 4/27/2020 8:14:12 AM | A | PASS |
|
|
correction notice given to park manager 5 days given to start proceedings to pull permit and get inspections...park ordiinance is no tampering to park pedistal allowed
|
ELE19-03639
| Electrical Rough-In | 4/26/2020 | 4/27/2020 | 4/27/2020 7:03:09 AM | P | CANC |
|
|
first floor ceiling drops Phone #: ###-#### >> Inspection requested via web by Todd Hall Inspection cancelled from web by: Todd Hall
|