ELE00-01010
| Final | 4/27/2000 | 4/28/2000 | 4/28/2000 12:00:00 AM | A | PASS |
|
|
John ###-#### Completed 4/28/00 12:11:36 PM
|
ELE00-01079
| Electrical Rough-In | 4/28/2000 | 4/28/2000 | 4/28/2000 12:00:00 AM | A | PART |
|
|
PVC groundwork in trench, ok.
|
ELE00-01508
| Permanent Service | 4/28/2000 | 4/28/2000 | 4/28/2000 12:00:00 AM | P | FAIL |
|
|
changed out service, disconnect and meters on the back of the apartment. Jake ###-#### NEC 250-96 (a) NEC 250-140 NEC 250-24 (a) (5) Need load calculations for service 5/1/00 3:40:48 PM
|
ELE00-00700
| Permanent Service | 4/28/2000 | 4/28/2000 | 4/28/2000 12:00:00 AM | P | FAIL |
|
|
Jeri ###-#### #14 Correction posted NEC 551-71 all 125-volt single phase 20 amp receptacles shall be GFCI protected also inspector needs to see male plug for camper. 5/1/00 3:40:19 PM
|