Inspections for the day of: Tuesday, April 28, 2009.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD06-02303 FIRE-Final Inspection4/27/20094/28/20094/28/2009 4:58:09 PMAPART
Remaining items include #17 (10) telephone line at the fire command center, #93 elevator signage, fire alarm descriptor at the FACP for sprinkler supervision per TOC. letter item six. Some issues corrected while on site including fire stop at penetrations on the 3rd, 4th, and 9th floors, EM light repair at the 9th floor west stairway, correct hardware installed at the basement west exit door, building plan schematic provided at the command center, missing escutcheon installed at the 17th floor stairway. EM lighting and exit signage tested okay via generator power. Project related shell alarm and sprinkler permits finaled.
FIR08-00461 INSP-Final Inspection4/28/20094/28/20094/28/2009 4:45:26 PMPPASS
Shell sprinkler work okayed for final.
FIR08-00018 INSP-Final Inspection4/28/20094/28/20094/28/2009 4:44:05 PMPPASS
Shell fire sprinkler work approved for final per walkthrough by T. Frost and completion of correction notice items including the installation of quick opening devices at the 3rd and 4th level dry systems. Dry system water delivery time at the 4th floor with calculated volume of 752.22 gallons per plan approved by M. Senteno.
FIR08-00461 INSP-Sprinkler Rough-in/Hydro4/28/20094/28/20094/28/2009 4:35:08 PMPPART
See activities under project related FIR08-00018 for the majority of inspections completed including the same scope of work for this permit.
FIR07-00507 INSP-Final Inspection4/28/20094/28/20094/28/2009 4:30:26 PMPPASS
Demo permit finaled.
FIR09-00127 INSP-Sprinkler Rough-in/Hydro4/27/20094/28/20094/28/2009 4:28:59 PMPPART
Pressure testing for the new preaction system completed okay, per NFPA 13 pneumatic testing for the single interlock system is not required.
FIR09-00023 INSP-Final Inspection4/24/20094/28/20094/28/2009 4:26:52 PMAPASS
Items on correction notice have been repaired and passed final inspection, knox box installed, record of completion recieved, permit finaled.
BLD09-00490 FIRE-Final Inspection4/27/20094/28/20094/28/2009 12:00:00 AMAPASS
josh Phone #: ###-####//pass fire life/safety per Forrest France