Inspections for the day of: Thursday, April 28, 2011.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorSteven Webb
Title 
Phone #794-9491
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC09-00352 General Inspection4/28/20114/28/20114/28/2011 3:28:22 PMPPASS
Controls in place, vegetative cells along the river are working fine, water slowing down by berms at cell perameters. No major problems observed.
ESC10-00689 General Inspection4/28/20114/28/20114/28/2011 3:09:37 PM PASS
No problems observed.
ESC11-00163 General Inspection4/28/20114/28/20114/28/2011 3:01:18 PMPPART
Verbal correction-top dressing on east entrance.
ESC10-00600 General Inspection4/28/20114/28/20114/28/2011 1:32:00 PM PASS
Area around new bridge has been hydroseeded, other area remains bare but grading activities being performed to prepare the area for seeding. Area under the bridge has slope and runoff protection in place.
ESC10-00743 General Inspection4/28/20114/28/20114/28/2011 1:07:52 PM PASS
Staging Area, appears ok, no problems observed.
ESC10-00611 General Inspection4/28/20114/28/20114/28/2011 7:52:45 AM DONE
Needs 70% re-vegetation.