FIR15-00009
| INSP-Final Inspection | 4/27/2015 | 4/28/2015 | 4/28/2015 3:28:40 PM | P | PART |
|
|
Functional testing of new Alarm panel and radio transmitter complete. Verified NETCON, duct SD shut down of HVAC, all tampers, flows, and power troubles accurately reported panel and central station. Need document box, signage on door to panel and map of initiating devices posted at FACP to complete.
|
FIR14-00531
| INSP-Sprinkler Rough-in | 4/27/2015 | 4/28/2015 | 4/28/2015 11:48:06 AM | A | PART |
|
|
3rd floor hallways OK to cover. See drawings for specific area of coverage.
|
BLD15-01170
| FIRE-Final Inspection | 4/27/2015 | 4/28/2015 | 4/28/2015 10:44:50 AM | A | FAIL |
|
|
Exit sign and emergency lighting to be fixed. Occupant to provide 5 fire extinguishers with current inspection tag and mount 48" along exit routes throughout. Verified no racking permit required.
|
FIR14-00430
| INSP-Sprinkler Rough-in | 4/24/2015 | 4/28/2015 | 4/28/2015 9:56:50 AM | A | PART |
|
|
Rough-in of parking garage complete. Areas with hard lid ok to cover. One drop to be fixed to maintain 6' min separation (see plan) and a couple lines to be straightened from ceiling contractor disturbing/twisting when installing ceiling grid. Before final ensure temp construction walls are demolished or sprinkler lines/heads will need to be adjusted.
|