Inspections for the day of: Thursday, April 28, 2016.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR16-00052 INSP-Sprinkler Rough-in4/27/20164/28/20164/29/2016 6:44:16 AMAPART
Thrust blocks are installed at the first 45's. All of the rest of the fittings are mechanically secured. The run of pipe from the 90 to the riser has been lowered 3" but is still 3" too high. I spoke to Jim Danes and he is going to follow up on whether they are going to lower the pipe or berm over it.
BLD15-01987 FIRE-Final Inspection4/27/20164/28/20164/28/2016 2:40:03 PMPFAIL
One of the eight new HVAC units that required a duct smoke detector now needs a FIR permit for the tie into the existing fire alarm system as per the IMC. Once connected to the fire alarm system the function/installation of the detector will need to be verified.
BLD15-04143 FIRE-Final Inspection4/27/20164/28/20164/28/2016 2:39:31 PMPFAIL
One of the eight new HVAC units that required a duct smoke detector now needs a FIR permit for the tie into the existing fire alarm system as per the IMC. Once connected to the fire alarm system the function/installation of the detector will need to be verified.
BLD16-00684 FIRE-Final Inspection4/28/20164/28/20164/28/2016 2:26:45 PMPFAIL
Relocate the exit sign/emergency light as discussed, provide permit for changing the Display(merch) area from light hazard to ordinary hazard, provide sprinkler analysis to Tim Frost, get Racking Permit or modify racks and storage as per Tim Frost and myselfs discussions.
FIR15-00905 INSP-Sprinkler Rough-in/Hydro4/28/20164/28/20164/28/2016 1:14:42 PMPPASS
Overhead hydro passed. Previous corrections have been addressed. Riser not finished yet (FDC) or alarm interconnections.
FIR16-00131 INSP-Sprinkler Rough-in4/28/20164/28/20164/28/2016 1:13:13 PMPPART
Rough-in for the Hanger area passed, just need bracing for the northwest foam diffusser finished up. General rough-in for the office area overhead piping is complete. Will need another rough-in inspection when all of the drops are cut/installed. Riser room/fire pump room is not complete. Need low point drain on the north main.
BLD16-00442 FIRE-Final Inspection4/27/20164/28/20164/28/2016 10:38:28 AMAPASS
Life safety passed