MEC96-00743
| INSP - Framing/ Rough-in | 4/29/1996 | 4/29/1996 | 4/29/1996 12:00:00 AM | P | PASS |
|
|
THE DUCT ABOVE CEILING IS DONE WAITING FOR CEILING TO BE PUT IN
|
MEC96-01256
| INSP - Final | 4/29/1996 | 4/29/1996 | 4/29/1996 12:00:00 AM | P | PART |
|
|
Y.M.C. IS DONE WITH THERE PART OF THE PROJECT. BUT CAN'T FINAL THIS TIL THE PLUMBERS HAVE CHANGED THE GAS PIPING TO A 2# SYSTEM AND THEY CALL IN FOR A FINAL. THEN I WILL FINAL THE JOB.
|
MEC96-01256
| INSP - Final | 4/29/1996 | 4/29/1996 | 4/29/1996 12:00:00 AM | P | PART |
|
|
Y.M.C. IS DONE WITH THERE PART OF THE PROJECT. BUT CAN'T FINAL THIS TIL THE PLUMBERS HAVE CHANGED THE GAS PIPING TO A 2# SYSTEM AND THEY CALL IN FOR A FINAL. THEN I WILL FINAL THE JOB.
|