ELE12-02665
| ELE-Aging Inspection | 4/29/2015 | 4/29/2015 | 5/1/2015 3:36:17 PM | | DONE |
|
|
Waiting for review on listing
|
ELE14-01072
| Final | 4/29/2015 | 4/29/2015 | 4/30/2015 9:36:38 AM | P | PASS |
|
|
Must check in with security at gate of Verizon switch building. Tower gate code should be 1256. Phone #: ###-#### Inspection requested via web by Krista Ratterree Final ok
|
ELE15-00032
| Final | 4/29/2015 | 4/29/2015 | 4/29/2015 5:34:34 PM | P | PASS |
|
|
Todd Phone #: ###-#### Final ok
|
ELE15-00930
| Rough-In Permanent Service | 4/29/2015 | 4/29/2015 | 4/29/2015 5:04:02 PM | P | PASS |
|
|
cody is the onsite contact at ###-#### Phone #: ###-#### Inspection requested via web by Tracy Robertson Rough in ok cover p/s u/g n ok
|
ELE15-01095
| Electrical Rough-In | 4/28/2015 | 4/29/2015 | 4/29/2015 4:20:01 PM | P | PASS |
|
|
Contact: Cody Cannon. Hard lid ceiling inspection please Phone #: ###-#### Inspection requested via web by Deb Gooden Walls and hardlid rough in ok cover
|
ELE15-00565
| Electrical Rough-In | 4/29/2015 | 4/29/2015 | 4/29/2015 3:48:03 PM | P | PASS |
|
|
grid insp // Ron ###-#### Grid rough in ok cover
|
ELE15-00858
| Final | 4/28/2015 | 4/29/2015 | 4/29/2015 3:27:35 PM | P | PASS |
|
|
Please notify Greg at the number listed prior to arrival. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Open boxes in ceiling for speakers. Final ok
|
ELE15-00897
| Final | 4/29/2015 | 4/29/2015 | 4/29/2015 3:14:02 PM | P | PART |
|
|
Phone #: ###-#### Inspection requested via web by JENNY EMEL Must inspect cubicals when complete. Temp final ok
|
ELE15-01194
| Electrical Rough-In | 4/29/2015 | 4/29/2015 | 4/29/2015 2:26:38 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Brad Girard Masterbath remodel rough in ok cover
|
ELE15-00426
| Final | 4/29/2015 | 4/29/2015 | 4/29/2015 1:59:00 PM | P | PASS |
|
|
Holes are patched Phone #: ###-#### Inspection requested via web by daniel bibikov Final ok
|
ELE15-01063
| Final | 4/29/2015 | 4/29/2015 | 4/29/2015 1:32:55 PM | P | FAIL |
|
|
The separate contractor hired by the homeowner to do the corrections cited by the inspector during the first EvenGreen rough in inspection has completed his work. The permit that he needed to pull and did not, has been filed properly and now finaled.
The inspection "fails" connected to this permit are not the work of EvenGreen Technology, nor were the inspections that failed requested by EvenGreen Technology. Our work has been passed with no issues by Boise City inspector, and this final is the only final that we have requested. Phone #: ###-#### Inspection requested via web by Ryan King Permit search does not show record of another permit by JDF Electric for repairs.
|
ELE15-00571
| Rough-In Permanent Service | 4/28/2015 | 4/29/2015 | 4/29/2015 1:27:48 PM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Heath Thomas Rough in ok cover p/s u/g n ok
|
ELE15-01015
| Electrical Rough-In | 4/28/2015 | 4/29/2015 | 4/29/2015 8:49:54 AM | A | PASS |
|
|
We are requesting a ceiling rough-in inspection for tomorrow 4/29/15 during the AM. Our onsite contact is Rich @ ###-####. Thank you!! Phone #: ###-#### Inspection requested via web by Clint Tate Grid IDF room only rough in ok cover
|
ELE15-00426
| Final | 4/28/2015 | 4/29/2015 | 4/29/2015 8:32:58 AM | A | FAIL |
|
|
Key will be in the front receptacle box for access. Thank you Phone #: ###-#### Inspection requested via web by daniel bibikov Drywall repair not complete
|
ELE15-01179
| Rough-In Permanent Service | 4/28/2015 | 4/29/2015 | 4/28/2015 7:44:34 AM | A | CANC |
|
|
>> Inspection requested via web by Rowdy Monroe Inspection cancelled from web by: Rowdy Monroe
|