FIR14-00708
| INSP-Sprinkler Rough-in | 4/29/2015 | 4/29/2015 | 4/29/2015 4:40:41 PM | P | PART |
|
|
Hard lids only at 3rd floor hallway and common room ok to cover. Advised that current drops for drop ceiling areas look overspaced, contractor to adjust as needed before RTC for drop ceiling. Storage room by elevator still pending a sprinkler drop.
|
FIR14-00869
| INSP-Final Inspection | 4/29/2015 | 4/29/2015 | 4/29/2015 1:39:07 PM | P | PASS |
|
|
Scope of work complete. Permit Finaled
|
FIR14-00815
| INSP-Sprinkler Rough-in | 4/29/2015 | 4/29/2015 | 4/29/2015 12:21:11 PM | P | PART |
|
|
Tenting inspection complete 4th floor, sec 2 living units only with the exception of RMs 414, 415, 416 to be inspected at a later date. The following correction notice items were fixed on the spot: Rm 408 pipe in contact with exhaust vent pipe, supplied insulation between Rm 412 pipe in contact with exhaust vent pipe in two spots, supplied insulation between. Rms 413, 411 and 406 had sections unfinished, completed by end of inspection.
|
BLD15-00799
| FIRE-Final Inspection | 4/29/2015 | 4/29/2015 | 4/29/2015 10:25:51 AM | P | PASS |
|
|
Fire life safety Pass.
|
FIR14-00917
| INSP-Final Inspection | 4/28/2015 | 4/29/2015 | 4/29/2015 9:29:48 AM | A | PASS |
|
|
Scope of work complete. Permit Finaled.
|
FIR14-00869
| INSP-Supply line flush | 4/28/2015 | 4/29/2015 | 4/29/2015 9:29:05 AM | A | PASS |
|
|
Scope of work complete. Flush of underground completed. Permit Finaled.
|