ELE20-01177
| Final | 4/2/2020 | 4/3/2020 | 4/3/2020 2:32:38 PM | P | PASS |
|
|
Dave will be on site - ###-#### Phone #: ###-#### Inspection requested via web by Arielle Hendricks...images of work done sent and verified...disconnect and breaker sized accordingly...ok to final
|
ELE19-04265
| Final | 4/3/2020 | 4/3/2020 | 4/3/2020 2:23:19 PM | P | PASS |
|
|
Shane- per Tom ok to schedule Phone #: ###-####... p/s u/g reconnect ok
|
ELE20-01184
| Rough-In Permanent Service | 4/3/2020 | 4/3/2020 | 4/3/2020 12:10:15 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Robert Murray... rough ok to cover p/s u/g new ok
|
ELE20-00509
| Final | 4/3/2020 | 4/3/2020 | 4/3/2020 10:21:17 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Rodney Monroe..ok to final
|
ELE20-00026
| Final | 4/2/2020 | 4/3/2020 | 4/3/2020 10:05:25 AM | A | PASS |
|
|
Woody- **cleared*** Phone #: ###-####... ok to final
|
ELE20-00667
| Final | 4/2/2020 | 4/3/2020 | 4/3/2020 9:17:24 AM | A | PASS |
|
|
*Cleared* Chad Phone #: ###-####... wired transformer out of existing panel in main electrical rm of building...added transformer for 120/240V panel...no circuits out of new panel...job complete...ok to final
|
ELE20-01199
| Rough-In Permanent Service | 4/3/2020 | 4/3/2020 | 4/3/2020 8:50:59 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Troy Ballard... rough ok to cover p/s u/g new ok
|
ELE20-01151
| Electrical Rough-In | 4/2/2020 | 4/3/2020 | 4/2/2020 10:14:37 AM | A | CANC |
|
|
Underground and bonding for swimming pool. Access granted on right side of residence Phone #: ###-#### >> Inspection requested via web by Lars Johnson Inspection cancelled from web by: Lars Johnson
|