BLD08-00264
| FIRE-Final Inspection | 4/28/2010 | 4/29/2010 | | A | |
|
|
Jim Phone #: ###-####
|
BLD09-01723
| FIRE-Final Inspection | 4/30/2010 | 4/30/2010 | 5/3/2010 6:32:25 PM | P | NR |
|
|
|
FIR10-00058
| INSP-Final Inspection | 4/30/2010 | 4/30/2010 | 4/30/2010 1:25:11 PM | P | PASS |
|
|
Fire alarm permit finaled.
|
BLD10-00765
| FIRE-Final Inspection | 4/30/2010 | 4/30/2010 | 4/30/2010 1:15:03 PM | P | NR |
|
|
Post one PFE with current tag.
|
BLD10-00385
| FIRE-Final Inspection | 4/30/2010 | 4/30/2010 | 4/30/2010 12:42:07 PM | P | FAIL |
|
|
Hardware at several doors serving individual tanning rooms does not meet adopted code, missing plans on site, need permit status changed to "issued" prior to final- (currently "under review"), noted jobsite is not in condition for final at this time due to finishes in progress. Discussed issues with contractor- final to be scheduled Mon. 5/3 as agreed.
|
BLD10-00286
| FIRE-Final Inspection | 4/29/2010 | 4/30/2010 | 4/30/2010 12:34:29 PM | A | PASS |
|
|
Fire life safety passed with the exception of two EM lights to be repaired, one exit sign to be added as discussed- will verify at structural final. Also noted timer installation at "push to exit" buttons for the first floor lobby is underway.
|
FIR10-00174
| INSP-Final Inspection | 4/29/2010 | 4/30/2010 | 4/30/2010 12:30:08 PM | A | PASS |
|
|
Fire alarm work passed field inspection, permit finaled.
|