ESC12-00421
| Site Preparation | 4/30/2012 | 4/30/2012 | 5/8/2012 11:36:15 AM | | NR |
|
|
|
ELE12-00917
| Electrical Rough-In | 4/30/2012 | 4/30/2012 | 4/30/2012 3:19:48 PM | P | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by PAT MILLER
|
ELE12-00917
| Final | 4/30/2012 | 4/30/2012 | 4/30/2012 3:19:37 PM | P | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by PAT MILLER
|
ELE12-00828
| Final | 4/27/2012 | 4/30/2012 | 4/30/2012 3:19:03 PM | P | PASS |
|
|
We have completed the installation and are ready for a Final Inspection. Our Wireman that worked on the project is Kyle Sharp at ###-####. There should be someone home for the inspection in the PM. The Homeowner can be reached at ###-#### for access. Thank you Phone #: ###-#### >> Inspection requested via web by Clint Tate
|
ELE12-00800
| Final | 4/30/2012 | 4/30/2012 | 4/30/2012 3:18:45 PM | P | PASS |
|
|
Mike Phone #: ###-####
|
ELE12-00622
| Final | 4/30/2012 | 4/30/2012 | 4/30/2012 3:18:31 PM | P | PASS |
|
|
Mike Phone #: ###-####
|
ELE12-00891
| Electrical Rough-In | 4/30/2012 | 4/30/2012 | 4/30/2012 3:18:20 PM | P | PASS |
|
|
Neal Phone #: ###-#### ok
|
ELE11-02481
| Final | 4/30/2012 | 4/30/2012 | 4/30/2012 1:17:56 PM | P | PASS |
|
|
Mike Phone #: ###-####
|
ELE12-00907
| Temporary Service | 4/30/2012 | 4/30/2012 | 4/30/2012 1:17:40 PM | P | PASS |
|
|
thank you Phone #: ###-#### >> Inspection requested via web by Rowdy Monroe t/s u/g new ok
|
ELE12-00509
| Final | 4/26/2012 | 4/30/2012 | 4/30/2012 11:35:32 AM | A | PASS |
|
|
Final for bathroom remodel. Phone #: ###-#### >> Inspection requested via web by John Edwards
|
ELE12-00912
| Conference | 4/30/2012 | 4/30/2012 | 4/30/2012 11:35:20 AM | A | DONE |
|
|
Steve. Call prior to heading to the site. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy
|
ELE12-00858
| Final | 4/29/2012 | 4/30/2012 | 4/30/2012 11:35:03 AM | A | PASS |
|
|
Our Wireman that performed the work is Seth at ###-####. Thank you Phone #: ###-#### >> Inspection requested via web by Clint Tate
|
ELE12-00278
| Electrical Rough-In | 4/27/2012 | 4/30/2012 | 4/30/2012 11:34:50 AM | A | PASS |
|
|
Jeremy Phone #: ###-#### walls
|
ELE11-01900
| ELE-Aging Inspection | 4/30/2012 | 4/30/2012 | 4/30/2012 10:20:35 AM | | DONE |
|
|
|
ELE12-00842
| Electrical Rough-In | 4/28/2012 | 4/30/2012 | 4/30/2012 10:00:08 AM | A | PASS |
|
|
ceiling hard lid Phone #: ###-#### >> Inspection requested via web by Bryan McLaughlin ok
|
ELE12-00907
| Temporary Service | 4/27/2012 | 4/30/2012 | 4/30/2012 7:47:10 AM | A | CANC |
|
|
Thank you Phone #: ###-#### >> Inspection requested via web by Rowdy Monroe Inspection cancelled from web by: Rowdy Monroe
|
ELE09-01139
| Final | 4/26/2012 | 4/30/2012 | 4/30/2012 12:00:00 AM | A | CANC |
|
|
Ray Young Phone #: ###-####
|