FIR13-00064
| INSP-Final Inspection | 4/29/2013 | 4/30/2013 | 5/2/2013 4:41:51 PM | A | PASS |
|
|
Functional testing passed. Fire alarm permit finaled.
|
FIR13-00046
| INSP-Final Inspection | 4/26/2013 | 4/30/2013 | 4/30/2013 4:55:12 PM | P | DEFR |
|
|
Rescheduled 5/1 AM as agreed
|
BLD13-00868
| FIRE-Final Inspection | 4/30/2013 | 4/30/2013 | 4/30/2013 4:53:54 PM | P | PART |
|
|
Remodel work at nine new office rooms passed fire life safety inspection (NW corner and south central second floor). East side work is incomplete.
|
FIR13-00139
| INSP-Final Inspection | 4/30/2013 | 4/30/2013 | 4/30/2013 4:50:39 PM | P | PASS |
|
|
Scope of work finished. Fire sprinkler permit finaled.
|
BLD13-00728
| FIRE-Final Inspection | 4/29/2013 | 4/30/2013 | 4/30/2013 4:48:55 PM | A | PASS |
|
|
|
FIR13-00186
| INSP-Sprinkler Rough-in | 4/29/2013 | 4/30/2013 | 4/30/2013 4:48:11 PM | A | PART |
|
|
See dated annotations on approved plan set for areas inspected and okayed for cover. East side remodel work is not yet ready.
|
FIR13-00176
| INSP-Sprinkler Rough-in/Hydro | 4/29/2013 | 4/30/2013 | 4/30/2013 4:45:29 PM | A | PART |
|
|
Rough-in inspection completed satisfactory.
|
FIR13-00127
| INSP-Final Inspection | 4/29/2013 | 4/30/2013 | 4/30/2013 4:44:21 PM | A | PASS |
|
|
Fire sprinkler permit finaled. Inspection passed.
|