BLD13-01507
| FIRE-Sprinkler Rough-in | 4/30/2014 | 4/30/2014 | 4/30/2014 5:12:22 PM | P | PART |
|
|
Okay to cover overhead fire sprinkler work completed to date as marked on approved plans including endo #4.
|
BLD14-00664
| FIRE-Conference | 4/30/2014 | 4/30/2014 | 4/30/2014 5:10:45 PM | P | DONE |
|
|
Need to add fire sprinkler coverage at the HVAC closet in stair #3, and provide EM lighting at the top of stair #3.
|
FIR13-00597
| INSP-Sprinkler Rough-in | 4/30/2014 | 4/30/2014 | 4/30/2014 5:05:36 PM | P | PART |
|
|
Shop area overhead work passed rough-in inspection.
|
BLD14-00996
| FIRE-Final Inspection | 4/30/2014 | 4/30/2014 | 4/30/2014 4:57:39 PM | P | PASS |
|
|
Life safety inspection completed satisfactory. Tenant to post "door to remain..." signage at the main entry/exit prior to structural final.
|
BLD14-00734
| FIRE-Final Inspection | 4/29/2014 | 4/30/2014 | 4/30/2014 11:48:51 AM | A | PASS |
|
|
Scope of remodel work at the 14th floor okayed pending door seal at the south exit, provide EM lighting at stair #3. Fire extinguishers are due annual certification next month- elevator machine room PFE is overdue.
|
BLD14-00989
| FIRE-Final Inspection | 4/25/2014 | 4/30/2014 | 4/30/2014 12:00:00 AM | P | CANC |
|
|
Facundo Phone #: ###-#### - customer called in and canceled - will reschedule later in the week ///4-30-14ps
|