MEC96-00929
| INSP - Gas pressure test | 4/4/1996 | 4/4/1996 | 4/4/1996 12:00:00 AM | P | CANC |
|
|
transfer to J Sly
|
BLD95-01555
| INSP - Framing/Rough-in | 4/4/1996 | 4/4/1996 | 4/4/1996 12:00:00 AM | P | FAIL |
|
|
PRE-FRAMING. AREA C corridors and elevator shaft have been compromised. Letter of Transmittal sent 04/05/96
|
BLD95-02164
| INSP - Footings | 4/4/1996 | 4/4/1996 | 4/4/1996 12:00:00 AM | P | FAIL |
|
|
poured w/o insp. Special Inspector did look at it and will sign off as to that pour. Notified Super not to pour until inspected
|
BLD96-00761
| INSP - Roof | 4/3/1996 | 4/4/1996 | 3/31/1996 12:00:00 AM | A | PASS |
|
|
04/03/96 342 - ROOF START
|
BLD1052379
| INSP - Final | 4/3/1996 | 4/4/1996 | 3/31/1996 12:00:00 AM | A | FAIL |
|
|
04/03/96 342 - egress window, caulk hvac boots to deck, comply w/bcec , mech final
|
BLD95-01694
| INSP - Conference | 4/3/1996 | 4/4/1996 | 3/31/1996 12:00:00 AM | P | NH |
|
|
04/03/96 342 - CONF. ON STAIRS. left phone # and looked at stairs again. This is the problem child in Hi
|