Inspections for the day of: Monday, April 4, 2016.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR16-00145 INSP-Sprinkler Rough-in/Hydro4/4/20164/4/20164/4/2016 3:29:38 PMPPART
Overhead for just the main piping passed except I need verification that the lateral siesmis bracing can be attatched to the bottom chord of the truss/girder. Riser nipples not instlled or attached yet. The overhead hydro failed due to a visible loss of pressure at the guage.
FIR15-00905 INSP-Sprinkler Rough-in/Hydro4/4/20164/4/20164/4/2016 3:19:53 PMPPART
Plan modifications are needed for these next items. Part of the rough-in is passed in the attic but one Attic Sprinkler is overspaced from a draftstop. Attice Heads have been installed in the overbuild leading to the front canopy. The lower sprinkler system has multiple addtional fittings and atleast on elevation change. Most of the changes noted were in the remote area on in the piping leading to the remote area. Overhead hydro canceled until changes and modifications have been approved and performed.
FIR15-00709 INSP-Sprinkler Rough-in4/4/20164/4/20164/4/2016 2:57:00 PMPCANC
4th floor insulation was not ready til late in the afternoon when I was not available for the inspection. I rescheduled for tomorrow morning early.
BLD15-02108 FIRE-Final Inspection4/1/20164/4/20164/4/2016 2:30:31 PMAFAIL
Can't perform life safety until the project related hood suppression permit is finaled. Per scott and my discussion the new hood and duct smoke detector do not need to be connected to the existing fire alarm system in the day care at the south end of the building due to an existing 4 hour wall that provides separation.
FIR16-00118 INSP-Sprinkler Rough-in4/4/20164/4/20164/4/2016 2:25:55 PMPCANC
Rescheduled for tomorrow morning
FIR16-00060 INSP-Sprinkler Rough-in/Hydro4/4/20164/4/20164/4/2016 2:25:23 PMPCANC
Rescheduled for tomorrow morning
BLD15-01780 FIRE-Final Inspection4/4/20164/4/20164/4/2016 1:32:47 PMPPASS
Life safety passed
NAF16-00024 INSP-Sprinkler Rough-in3/31/20164/4/20164/4/2016 11:01:29 AMAFAIL
Existing upright sprinkler coverage along the south wall, over the restrooms/office are overspaced off of the wall. I measure them at 8'-4". Part of the sprinkles pendants have been covered prior to inspection. I posted a "do not cover" sticker on the window.
BLD16-00927 FIRE-Final Inspection3/31/20164/4/20164/4/2016 10:22:02 AMAFAIL
Provide permit for hood system modifications, provide re-certification for fire extinguishers, repair all exit signs and emeregency lights,cover all exposed electrical outlets, remove dead bolt on storage room under stairs.
BLD15-03303 FIRE-Final Inspection4/1/20164/4/20164/4/2016 9:06:07 AMAFAIL
No city approved plans on site. I spoke to the tenant and went over life safety requirements.
BLD15-04030 FIRE-Final Inspection4/1/20164/4/20164/4/2016 8:34:34 AMAPASS
Life safety passed
FIR15-00471 INSP-Sprinkler Rough-in3/31/20164/4/20164/4/2016 8:28:22 AMACANC
requesting an inspection at the Holiday Inn Express on the 4th Floor
Type of inspection -Rough to cover.
The contact is Robert Mullins - ###-####. Phone #: ###-#### >> Inspection requested via web by Kay Haney Inspection cancelled from web by: Stan Beus