Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR10-00543 INSP-Sprinkler Rough-in/Hydro4/5/20114/5/20114/5/2011 3:31:29 PMPPASS
The underground hydro test passed.
FIR10-00443 INSP-Final Inspection4/4/20114/5/20114/5/2011 3:30:14 PMAFAIL
One of the new earthquake bracing attachment points needs to be taken to the deck as discussed. Also the sidewall sprinkler heads are listed to be installed 6" to 12" below the deck. Some of them are actually installed 4" below the deck.
FIR11-00132 INSP-Final Inspection4/5/20114/5/20114/5/2011 1:38:17 PMPPASS
Permit finaled
BLD11-00272 FIRE-Final Inspection4/5/20114/5/20114/5/2011 1:36:23 PMPPASS
life safety passed
BLD10-01234 FIRE-Final Inspection4/5/20114/5/20114/5/2011 1:09:28 PMPPART
A temporary was given with Scott's permission until the as-built building drawings have been approved. A follow up inspection will be required to verify the new approved plans have been complied with.
FIR10-00656 INSP-Final Inspection4/5/20114/5/20114/5/2011 11:19:17 AMPPASS
permit finaled
BLD11-00272 FIRE-Final Inspection4/4/20114/5/20114/5/2011 11:13:09 AMAFAIL
Provide ADA hardware for the pocket door and provide exit discharge lighting as per plan.
FIR11-00125 INSP-Final Inspection4/4/20114/5/20114/5/2011 10:15:08 AMAPASS
Permit finaled
BLD11-00328 FIRE-Final Inspection4/4/20114/5/20114/5/2011 9:16:05 AMAPASS
life safety passed
BLD10-02989 FIRE-Final Inspection4/4/20114/5/20114/5/2011 8:34:16 AMAPASS
life safety passed.