Inspections for the day of: Tuesday, April 5, 2016.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR15-00709 INSP-Sprinkler Rough-in/Hydro4/4/20164/5/20164/5/2016 1:57:57 PMAPASS
4th floor and 3rd floor piping above Resident Rooms is ok to cover. Hall way piping is not complete and can not be covered. Robert and I spoke about two rooms on each floor where the sidewall heads are overspaced. This issue is to be addressed prior to cover either through new heads/piping or a change in sidewall heads. Either direction taken will need to be approved prior to cover.
ESC15-01567 General Inspection4/5/20164/5/20164/5/2016 12:55:09 PMPPASS
I noted no track out at the exterior of the building and none going into the new floor drains on the interior at this time.
FIR16-00118 INSP-Sprinkler Rough-in/Hydro4/4/20164/5/20164/5/2016 11:18:18 AMAPART
The 2nd floor piping above the hardlids/corridors is ok to cover. Rough-in passed.
FIR16-00060 INSP-Sprinkler Rough-in/Hydro4/4/20164/5/20164/5/2016 11:17:16 AMAPART
The 5th floor hydro test passed. Also the rough-in inspection for the gridded areas passed. Piping above the gridded areas can be covered. One branch line restraint installed while I waited.
BLD16-00832 FIRE-Final Inspection4/4/20164/5/20164/5/2016 10:37:41 AMAFAIL
Not all of the city approved documents appeared to be here. Missing the floor plans and notes. Max storage height on the scope of work says 10'. Actual storage height has been exceeded in the store. No actual inspection could be performed.
FIR16-00145 INSP-Sprinkler Rough-in/Hydro4/4/20164/5/20164/5/2016 10:04:59 AMAPASS
Overhead r/i and hydro test for the 8" and 6" mains passed.