ELE01-01088
| Electrical Rough-In | 4/5/2001 | 4/6/2001 | 4/6/2001 12:00:00 AM | A | PART |
|
|
Dave ###-#### conf only 4/6/2001 12:10:03 PM
|
ELE01-00661
| Electrical Rough-In | 4/5/2001 | 4/6/2001 | 4/6/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 04/05/2001 at 09:42:40. Contact: ###-####.
|
ELE01-01100
| Temporary Service | 4/5/2001 | 4/6/2001 | 4/6/2001 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 04/05/2001 at 14:53:32. Contact: ###-####. clearance and grounding 4/6/2001 10:32:56 AM
|
ELE01-00721
| Final | 4/5/2001 | 4/6/2001 | 4/6/2001 12:00:00 AM | A | PASS |
|
|
###-#### P/S O/H R Ok 4/6/2001 8:48:31 AM
|
ELE01-00873
| Rough-In Permanent Service | 4/6/2001 | 4/6/2001 | 4/6/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 04/06/2001 at 09:10:34. Contact: ###-####. P/S U/G add on ok 4/6/2001 3:58:16 PM
|
ELE01-01100
| Temporary Service | 4/6/2001 | 4/6/2001 | 4/6/2001 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 04/06/2001 at 10:20:34. Contact: ###-####. T/S U/G N Ok 4/6/2001 1:41:28 PM
|
ELE00-03656
| Electrical Rough-In | 4/6/2001 | 4/6/2001 | 4/6/2001 12:00:00 AM | P | PASS |
|
|
R/I PAGER ###-#### BRIAN
|
ELE01-01100
| Final | 4/6/2001 | 4/6/2001 | 4/6/2001 12:00:00 AM | P | PASS |
|
|
Added by Inspector: 336 On 4/6/2001 1:41:40 PM
|