Inspections for the day of: Thursday, April 6, 2006.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR05-00594 INSP-Sprinkler Rough-in4/6/20064/6/20064/6/2006 4:40:58 PMPPART
The 11th floor overhead rough-in is good for cover at the drop ceiling areas.
BLD06-00015 FIRE-Final Inspection4/6/20064/6/20064/6/2006 4:21:17 PMPDEFR
Inspection to be completed 4/7 in the am as discussed.
BLD05-00978 FIRE-Final Inspection4/5/20064/6/20064/6/2006 4:20:31 PMPDEFR
Inspection to be completed 4/7
FIR05-00688 INSP-Final Inspection4/6/20064/6/20064/6/2006 4:15:27 PMPPASS
Fire sprinkler permit finaled.
FIR06-00225 INSP-Final Inspection4/5/20064/6/20064/6/2006 4:12:00 PMAPASS
Fire sprinkler demo work has been completed according to permit scope, permit finaled.
BLD05-03323 FIRE-Final Inspection4/5/20064/6/20064/6/2006 3:38:25 PMPPASS
Fire life safety is acceptable, inspection passed.
FIR05-00894 INSP-Final Inspection4/4/20064/6/20064/6/2006 3:37:30 PMPPASS
Fire alarm work passed inspection, duct detector supervisory descriptions at the panel to be added today.
FIR06-00012 INSP-Final Inspection4/6/20064/6/20064/6/2006 3:34:59 PMPPASS
Fire sprinkler work is satisfactory, permit finaled.
FIR05-00297 INSP-Sprinkler Rough-in/Hydro4/5/20064/6/20064/6/2006 3:06:22 PMAFAIL
Overhead hydrostatic test failed to maintain pressure on the 4th floor and the standpipe, basement system not tested at this time.
FIR05-00712 INSP-Final Inspection4/5/20064/6/20064/6/2006 2:51:06 PMPFAIL
Partial test of the ground level phase 2 only, audibility is lacking the required dB in the mens and womens restrooms, SD needs relocation at the electrical room, one SD is overspaced at the NW corridor, provide date on batteries at the nac panel, HC rooms tested okay, one incorrect cd rating at the storage room was repaired while on site.
FIR05-00449 INSP-Alarm Testing4/4/20064/6/20064/6/2006 2:44:48 PMAPART
Partial test of detection and notification devices on the ground level, intermediate mech. mezzanine, and 2nd floors, need to verify audibility requirements are met in the mech. mezz., no sprinkler related items tested at this time.
FIR05-00804 INSP-Alarm Testing4/4/20064/6/20064/6/2006 2:39:51 PMAFAIL
UV/IR detection device failed upon activation to shut down equipment and report as an alarm condition.