FIR05-00594
| INSP-Sprinkler Rough-in | 4/6/2006 | 4/6/2006 | 4/6/2006 4:40:58 PM | P | PART |
|
|
The 11th floor overhead rough-in is good for cover at the drop ceiling areas.
|
BLD06-00015
| FIRE-Final Inspection | 4/6/2006 | 4/6/2006 | 4/6/2006 4:21:17 PM | P | DEFR |
|
|
Inspection to be completed 4/7 in the am as discussed.
|
BLD05-00978
| FIRE-Final Inspection | 4/5/2006 | 4/6/2006 | 4/6/2006 4:20:31 PM | P | DEFR |
|
|
Inspection to be completed 4/7
|
FIR05-00688
| INSP-Final Inspection | 4/6/2006 | 4/6/2006 | 4/6/2006 4:15:27 PM | P | PASS |
|
|
Fire sprinkler permit finaled.
|
FIR06-00225
| INSP-Final Inspection | 4/5/2006 | 4/6/2006 | 4/6/2006 4:12:00 PM | A | PASS |
|
|
Fire sprinkler demo work has been completed according to permit scope, permit finaled.
|
BLD05-03323
| FIRE-Final Inspection | 4/5/2006 | 4/6/2006 | 4/6/2006 3:38:25 PM | P | PASS |
|
|
Fire life safety is acceptable, inspection passed.
|
FIR05-00894
| INSP-Final Inspection | 4/4/2006 | 4/6/2006 | 4/6/2006 3:37:30 PM | P | PASS |
|
|
Fire alarm work passed inspection, duct detector supervisory descriptions at the panel to be added today.
|
FIR06-00012
| INSP-Final Inspection | 4/6/2006 | 4/6/2006 | 4/6/2006 3:34:59 PM | P | PASS |
|
|
Fire sprinkler work is satisfactory, permit finaled.
|
FIR05-00297
| INSP-Sprinkler Rough-in/Hydro | 4/5/2006 | 4/6/2006 | 4/6/2006 3:06:22 PM | A | FAIL |
|
|
Overhead hydrostatic test failed to maintain pressure on the 4th floor and the standpipe, basement system not tested at this time.
|
FIR05-00712
| INSP-Final Inspection | 4/5/2006 | 4/6/2006 | 4/6/2006 2:51:06 PM | P | FAIL |
|
|
Partial test of the ground level phase 2 only, audibility is lacking the required dB in the mens and womens restrooms, SD needs relocation at the electrical room, one SD is overspaced at the NW corridor, provide date on batteries at the nac panel, HC rooms tested okay, one incorrect cd rating at the storage room was repaired while on site.
|
FIR05-00449
| INSP-Alarm Testing | 4/4/2006 | 4/6/2006 | 4/6/2006 2:44:48 PM | A | PART |
|
|
Partial test of detection and notification devices on the ground level, intermediate mech. mezzanine, and 2nd floors, need to verify audibility requirements are met in the mech. mezz., no sprinkler related items tested at this time.
|
FIR05-00804
| INSP-Alarm Testing | 4/4/2006 | 4/6/2006 | 4/6/2006 2:39:51 PM | A | FAIL |
|
|
UV/IR detection device failed upon activation to shut down equipment and report as an alarm condition.
|