Inspections for the day of: Thursday, April 6, 2017.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRock A. Hudson
TitleELE-INSPECTOR
Phone #794-6794
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE17-00116 Electrical Rough-In4/6/20174/6/20174/6/2017 3:21:33 PMPPASS
Wall Rough-In Inspection
Contact Jon Novak
Thank you Phone #: ###-#### Inspection requested via web by Cathy Duchek
Checked phase 1 for TCO OK
ELE16-04108 Electrical Rough-In4/5/20174/6/20174/6/2017 2:07:38 PMPPASS
Rough-In Inspection for the gatehouse
Contact Dan Hutchinson
Thank you Phone #: ###-#### Inspection requested via web by Cathy Duchek
Walls and hardlids rough in ok cover
ELE17-00037 Electrical Rough-In4/5/20174/6/20174/6/2017 2:00:34 PMPPASS
Rough in inspection for Building 12
Contact Dan Hutchinson
Thank you Phone #: ###-#### Inspection requested via web by Cathy Duchek
Rough in ok cover
ELE17-00624 Electrical Rough-In4/5/20174/6/20174/6/2017 12:20:20 PMAPASS
Jason is the contact his cell no. ###-####. Inspection requested via web by Shawna Gates
2nd floor north and south grid rough in ok cover
ELE16-04017 Electrical Rough-In4/5/20174/6/20174/6/2017 10:26:45 AMAPASS
L1 Deck pour 4 Phone #: ###-#### Inspection requested via web by Debby Pierce
Area noted rough in ok cover
ELE16-01652 Electrical Rough-In4/5/20174/6/20174/6/2017 9:34:52 AMAPASS
Underground at north end of south wing.Please call when you are walking over early am would be great if that works for you. Phone #: ###-#### Inspection requested via web by John Rourke
Area noted rough in ok cover