Inspections for the day of: Thursday, April 6, 2017.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD17-00486 FIRE-Final Inspection4/5/20174/6/20174/6/2017 1:46:37 PMPPASS
Life safety passed
FIR17-00136 INSP-Sprinkler Rough-in4/6/20174/6/20174/6/2017 1:39:16 PMPPASS
Hard lids ok for cover
BLD16-02646 FIRE-Final Inspection4/5/20174/6/20174/6/2017 1:37:44 PMAPASS
Life safety passed.
FIR16-00824 INSP-Sprinkler Rough-in4/6/20174/6/20174/6/2017 1:37:17 PMPPASS
Re-routing of the underground piping has been approved. All sprinkler piping in the building can be covered.
FIR16-00823 INSP-Sprinkler Rough-in4/6/20174/6/20174/6/2017 1:37:16 PMPFAIL
The city approved plans for the rerouted underground supply piping have been provided but they do not match the actual installation. Revised plans showing the actual placement of pipe need to be provided to plan review. Second floor piping is still not tented yet.
FIR16-00284 INSP-Sprinkler Rough-in4/5/20174/6/20174/6/2017 9:43:58 AMAPASS
Unit 201 piping above soffits can be covered
FIR17-00115 INSP-Sprinkler Rough-in4/5/20174/6/20174/6/2017 9:41:58 AMAPASS
Piping above hardlids is ok for cover.